‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Aug 15, 2019

New edition of Building Code Requirements for Structural Concrete available

American Concrete Institute document includes major technical changes.

Codes and Standards | Aug 13, 2019

Coaching pays off for new managers

Study finds increased engagement and readiness for new roles.

Codes and Standards | Aug 12, 2019

New curtain wall design guidelines released

AAMA document includes mandatory language, optional language, and detailed technical commentary.

Codes and Standards | Aug 9, 2019

Cities modify density zoning to spur more affordable housing projects

Solutions include eliminating single-family zoning and allowing taller apartments in higher-density zones.

Codes and Standards | Aug 8, 2019

More designers focusing on acoustic properties of buildings

Recognition that structures should be acoustically satisfying.

Codes and Standards | Aug 6, 2019

New technology, aligning training with local trends among keys to workforce development

Construction industry must also invest in training, recruiting high school students.

Codes and Standards | Aug 1, 2019

Planners, city official rethink parking requirements on new projects

Reducing number of parking spots frees up land for ‘more purposeful’ uses.

Codes and Standards | Jul 31, 2019

USGBC-LA chooses first ‘Net Zero Accelerator’ technologies

Wide range of solutions address numerous environmental challenges.

Codes and Standards | Jul 30, 2019

Solar brokerage will provide financing for small/medium businesses

First to fund solar for smaller-scale commercial operations.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021