‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | May 20, 2019

Effort launched to develop better process for zero-carbon retrofits in multifamily sector

Rocky Mountain Institute, Dept. of Energy, California Energy Commission join forces.

Codes and Standards | May 20, 2019

Property lenders shouldn’t invest for 30 years in most of Florida, expert warns

Climate ignorance driving some ‘insane’ deals.

Codes and Standards | May 17, 2019

NIMBYism is the biggest multifamily construction barrier

National Apartment Assn. report assesses reasons for difficulty in creating more apartments.

Codes and Standards | May 17, 2019

Dept. of Energy to award up to $33.5 million for advanced construction R&D

Focus is on techniques to reduce energy bills.

Codes and Standards | May 16, 2019

Mixed reviews on targeted tax break for San Francisco neighborhood

“Twitter tax break” may have worsened some of the area’s problems.

Codes and Standards | May 15, 2019

OSHA inspections to increase, says Secretary of Labor

Newly hired inspectors getting up to speed.

Codes and Standards | May 14, 2019

Database records more than 1,360 K-12 school shooting incidents since 1970

Naval Postgraduate School program maps locations nationwide.

Codes and Standards | May 13, 2019

In many cities, downtown housing comes with a hefty premium

Urban core living costs hundreds of thousands more in largest U.S. cities.

Codes and Standards | May 7, 2019

San Francisco plan would require largest commercial buildings to use 100% renewable electricity

First in the U.S. mandate would be phased in from 2022 to 2030.

Codes and Standards | May 7, 2019

ABC says best practices can improve construction companies’ safety by 680%

Daily ‘toolbox safety talks’ were most effective safety measures.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021