‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Sep 25, 2017

How-to guide to renovating shopping centers available

E.U. research project focuses on energy efficiency and occupant comfort.

Codes and Standards | Sep 21, 2017

After construction crane collapses during Irma, regulations questioned

Cranes rated for 140 mph winds didn’t hold up to 100 mph gusts.

Codes and Standards | Sep 20, 2017

Energy efficiency measures pay off in some not-so-obvious ways

Access to better financing, tax incentives, rent premiums, among the benefits to greener buildings.

Codes and Standards | Sep 19, 2017

Benchmarking regulations prompt jump in green certified properties

2016 saw a slight rise in total certified U.S. green office space.

Codes and Standards | Sep 18, 2017

Changes likely to come to federal wetlands regulations

However, states may step up regulations as feds relax them.

Codes and Standards | Sep 14, 2017

Gentrification means a new mindset for city planners

Rising rents elicit reexamination of zoning principles.

Codes and Standards | Sep 13, 2017

OSHA issues extension for compliance with crane operator certification requirements

Comments on proposed rule sought through Sept. 29.

Codes and Standards | Sep 12, 2017

Washington, D.C. is first LEED Platinum city in the world

All city government buildings are powered by renewables.

Codes and Standards | Sep 11, 2017

Natural solutions would be most effective flood resilience policies for Houston

New green infrastructure should be part of rebuild.

Codes and Standards | Sep 8, 2017

Los Angeles luxury high-rise is first U.S. apartment building to achieve WELL Multifamily certification

Hollywood Proper Residences have verified indoor air and water quality features.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021