A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.
These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.
The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).
The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.
Related Stories
Codes and Standards | Oct 30, 2017
AIA revises architect scope documents in latest contract form release
Design-bid-build forms last updated in 2007.
Codes and Standards | Oct 26, 2017
Boston’s Old South Church asks tower developer for $19 million for casting shade
Request highlights ongoing conflict between developers and residents over right to sunshine.
Codes and Standards | Oct 24, 2017
Asphalt roofing design guide now available in digital form
Recently updated Modified Bitumen Design Guide can be viewed on smartphones and tablets.
Codes and Standards | Oct 23, 2017
Energy efficiency investments on the rise; will increase next year
Survey of facility management executives shows onsite renewables, energy storage will spike in 2018.
Codes and Standards | Oct 20, 2017
AIA contract document updates include new BIM, digital data provisions
Documents are structurally different from 2007, 2008 versions.
Codes and Standards | Oct 19, 2017
IAPMO seeks proposals for 2021 Uniform Plumbing Code, Uniform Mechanical Code
The deadline is March 16, 2018.
Codes and Standards | Oct 18, 2017
States impacted by hurricanes are improving their energy efficiency policies
Florida, Texas, rise in ACEEE state energy efficiency scorecard.
Codes and Standards | Oct 17, 2017
Updated versions of EnergyPlus and OpenStudio building energy modeling tools released
Open-source apps include enhancements for urban-scale modeling.
Codes and Standards | Oct 16, 2017
New, comprehensive insurance exhibit released in AIA 2017 contract document updates
Will allow AIA to make updates more frequently as insurance market changes.
Codes and Standards | Oct 12, 2017
New AIA contract document designates responsibilities for sustainable projects
Roles of architects, contractors outlined in E204–2017.