A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.
These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.
The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).
The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.
Related Stories
Codes and Standards | Nov 15, 2017
NBI stretch code a tool for accelerating efficiency standards
It provides a strategy to leapfrog minimum code requirements.
Codes and Standards | Nov 14, 2017
California bill would require purchase of low-carbon construction products
Contractors would have to source products based on greenhouse gas impact, not price, on state projects.
Codes and Standards | Nov 13, 2017
New AIA contract document for facility support services released
Updated form intended to be used with owner-architect agreements.
Codes and Standards | Nov 9, 2017
NIBS, NBI issue guidance document to help communities achieve energy goals
Outcome-based codes compliance path looks at building’s actual performance.
Codes and Standards | Nov 7, 2017
Underwriters Laboratories launches wellness certification
First certification program that verifies products’ compliance with the WELL Building Standard.
Codes and Standards | Nov 6, 2017
Registration now open for Canada’s first Zero Carbon Building (ZCB) program
Standard is designed to be applicable across many types of new and existing buildings.
Codes and Standards | Nov 6, 2017
AIA releases new architect commissioning document
It will be used with the standard form for owner/consultant contracts.
Codes and Standards | Nov 2, 2017
ASHRAE releases new version of Thermal Comfort Standard
Update includes calculations from direct solar radiation.
Codes and Standards | Nov 1, 2017
Drone users can now get instant authorization from FAA
Skyward offers app to receive permission for low altitude flights.
Codes and Standards | Oct 31, 2017
Real estate giant launches global tenant health and wellness certification initiative
Tishman Speyer will use Fitwel health certification system to guide building improvements.