‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Jul 22, 2020

New version of IAPMO’s Water Demand Calculator is available

Enhanced features include selection between single- and multifamily buildings.

Codes and Standards | Jul 22, 2020

Mobile app calculates sound transmission for wood-framed assemblies

American Wood Council tool for floor-ceiling assemblies.

Codes and Standards | Jul 22, 2020

Architecture billings remain in negative territory, begin to stabilize

Fewer architecture firms report declining billings this month.

Codes and Standards | Jul 20, 2020

N.Y. construction firm to pay $1.5 million to settle sexual harassment claim

Managers said to demand sex for pay and OT opportunities.

Codes and Standards | Jul 16, 2020

Tips to make optimal use of salvaged materials

Integrated teams, staging warehouse, and looking early and often, among recommendations.

Codes and Standards | Jul 15, 2020

Georgia gives the go-ahead for tall mass timber construction

Standards review scheduled to be completed by July 2021.

Codes and Standards | Jul 15, 2020

Softwood-lumber duties boost expenses amid COVID-19 outbreak

Little hope this year for resolution of trade dispute with Canada.

Codes and Standards | Jul 14, 2020

Metal Construction Assn. releases three EPD updates

Pertain to Metal Composite Materials, Insulated Metal Panels, and Roll Formed Aluminum and Steel Cladding.

Codes and Standards | Jul 13, 2020

5 must reads for the AEC industry today: July 13, 2020

4 technologies for improving building sanitation and tech's ever-evolving impact on the multifamily space.

Codes and Standards | Jul 9, 2020

Funding opportunity for field validation of high-impact building technologies

Dept. of Energy program targets dynamic interactions with electric grid.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021