‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Oct 7, 2020

More energy efficiency programs are encouraging zero-energy projects

At least 20 programs for new construction, major renovations emerge.

Codes and Standards | Oct 6, 2020

LEED, GBCI rating systems spur resilience-enhancing strategies

Expanded programs, resources address impact of climate change.

Codes and Standards | Oct 6, 2020

International Code Council to hold inaugural online education event

Week-long ICC Learn Live will include panel conversations, keynotes, and breakout sessions around key topics in building safety.

Codes and Standards | Oct 5, 2020

Guides addressing fenestration anchorage updated

First update to decade-old technical documents released.

Codes and Standards | Oct 1, 2020

Deadline extension for LEED 2009 project certifications

Delivery timeline delays due to COVID-19 pandemic prompt action.

Codes and Standards | Sep 29, 2020

New drinking water standard criteria further restricts lead leaching in plumbing products

Tightened standard applies to endpoint devices that dispense drinking water, and other plumbing components

Codes and Standards | Sep 29, 2020

Groups sue CDC over eviction moratorium

Natl. Apartment Assn. and New Civil Liberties Alliance want hearing by October.

Codes and Standards | Sep 24, 2020

Benefits of building enclosure commissioning include reduced costs

Savings achieved in less rework and fewer and shorter punch lists.

Codes and Standards | Sep 23, 2020

Intl. Code Council aims to stay ahead of new tech, efficiency trends, and resiliency

Passive survivability, social resiliency, and community health among the goals.

Codes and Standards | Sep 22, 2020

Air cleaners, chemical and UV treatments among tools to safeguard indoor air amid pandemic

Strategies augment social distancing, increased air flow to combat COVID-19 spread.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021