‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | May 26, 2020

Is CLT really a green solution?

Sustainability depends upon forest stewardship, product manufacturing process.

Codes and Standards | May 20, 2020

St. Louis is first Midwest city to pass building energy performance standard

Allows owners broad flexibility on how to achieve goals.

Codes and Standards | May 20, 2020

Supreme Court says Georgia cannot copyright its entire official code

Ruling may have implications for other states claiming copyright for building codes.

Codes and Standards | May 18, 2020

Strategies to reduce personal contact in multifamily properties

Design can improve health amid COVID-19 pandemic.

Codes and Standards | May 18, 2020

Canada Green Building Council says building industry lacks zero-carbon skills, knowledge

Net-zero target requires shift in thinking and practices.

Codes and Standards | May 18, 2020

California’s grid can support all-electric buildings

Load-shifting will help reduce peak demand.

Codes and Standards | May 15, 2020

European cities to revamp transportation after pandemic reopening

Road closures, new rules for public transit will be imposed.

Codes and Standards | May 14, 2020

Washington State construction industry restart plan has three phases

In state with earliest COVID-19 cases, advisory group developing priorities based on risk.

Codes and Standards | May 14, 2020

More mass timber beam and column options available in the U.S.

Freres Lumber unveils new line of structural elements suitable for high-rise buildings.

Codes and Standards | May 13, 2020

Researchers flag insufficient training for construction workers on healthcare projects

May contribute to fungal disease outbreaks that endanger patients

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021