Most top U.S. contractors rarely deliver projects on time: new study

Contractors

Most top U.S. contractors rarely deliver projects on time: new study

Struggles with supply chain disruptions, construction costs, and new sustainability requirements cause delays, according to a new study by XYZ Reality.


By Peter Fabris, Contributing Editor | June 26, 2023
Photo by Ricardo Gomez Angel on Unsplash
Photo by Ricardo Gomez Angel on Unsplash

About 63% of leading U.S. contractors are delivering projects out of schedule, according to a survey of over 300 C-suite executives and owners in the construction industry by XYZ Reality.

The study implies that the industry is struggling with significant backlogs due, in part, to avoidable defects, scan, and rework. The construction sector is also hampered by supply chain disruptions (cited by 52% of respondents), rising construction costs (43%), and meeting new sustainability requirements (36%).

Other reasons cited for falling short of schedule benchmarks include poor communication (45%), inexperienced workers (39%), and insufficient supervision (34%). This data suggests that a significant amount of human error is to blame, XYZ notes.

Design changes, or the misinterpretation of them, were also cited by about a quarter of respondents. To control costs and cope with industry challenges, contractors are increasingly looking to technology solutions such as augmented reality.

Related Stories

| Sep 24, 2012

$3.8-million athletic field and track opens in Glen Head, N.Y.

The complex also includes a new, one-story, multi-purpose building that serves as the main entry port to the athletic facilities.

| Sep 21, 2012

AAMA and WDMA release updated review and forecast that predicts industry trends

Significant volume is expected to return to the entry and interior door market as new construction demand is expected to grow at double-digit rates, outpacing remodeling and replacement activity as the housing market recovers.

| Sep 20, 2012

Mid-box retail study shows lack of available sites in Chicago

Existing supply is tight everywhere and almost non-existent in the most attractive zones.

| Sep 20, 2012

Forrester begins construction of freestanding cancer center in Montgomery County, Md.

The new 51,000-square-foot building will include two linear accelerator vaults for radiation equipment.

| Sep 19, 2012

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.

| Sep 19, 2012

ABI back into positive territory

South continues to lead regions in demand for design services.

| Sep 19, 2012

Sasaki opens office in Shanghai

Office supports firm’s present and future work in China, throughout Asia.

| Sep 18, 2012

MBMA partners with ORNL for whole building energy efficiency study

The results are intended to advance energy efficiency solutions for new and retrofit applications.

| Sep 18, 2012

MKK opens office in North Dakota

MKK is currently working on seven projects in North Dakota, including a hotel, restaurant, truck stop, office building, and apartment complex.

| Sep 18, 2012

Firestone Building Products launches new website

Deep product information and innovative customer support tools are highlights.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021