Most top U.S. contractors rarely deliver projects on time: new study

Contractors

Most top U.S. contractors rarely deliver projects on time: new study

Struggles with supply chain disruptions, construction costs, and new sustainability requirements cause delays, according to a new study by XYZ Reality.


By Peter Fabris, Contributing Editor | June 26, 2023
Photo by Ricardo Gomez Angel on Unsplash
Photo by Ricardo Gomez Angel on Unsplash

About 63% of leading U.S. contractors are delivering projects out of schedule, according to a survey of over 300 C-suite executives and owners in the construction industry by XYZ Reality.

The study implies that the industry is struggling with significant backlogs due, in part, to avoidable defects, scan, and rework. The construction sector is also hampered by supply chain disruptions (cited by 52% of respondents), rising construction costs (43%), and meeting new sustainability requirements (36%).

Other reasons cited for falling short of schedule benchmarks include poor communication (45%), inexperienced workers (39%), and insufficient supervision (34%). This data suggests that a significant amount of human error is to blame, XYZ notes.

Design changes, or the misinterpretation of them, were also cited by about a quarter of respondents. To control costs and cope with industry challenges, contractors are increasingly looking to technology solutions such as augmented reality.

Related Stories

| Nov 6, 2012

Honeywell donates first responder products for Hurricane Sandy relief and recovery efforts

Honeywell Humanitarian Relief Fund to provide aid to local employees affected by Hurricane Sandy.

| Nov 6, 2012

Uponor files patent infringement suit against Sioux Chief Manufacturing

Uponor is seeking damages and an injunction to prevent Sioux Chief from selling the PowerPEX F1960 Ring with Stop, which it believes violates Uponor’s patent.

| Nov 6, 2012

Simpson Strong-Tie donates $25K to hurricane support

The company will also be matching employees’ personal contributions to the Red Cross and other nonprofit disaster relief organizations.

| Nov 6, 2012

Goettsch Partners designs new tower in Shunde, China

200-meter-tall building will be located between Guangzhou and Hong Kong.

| Nov 5, 2012

Brasfield & Gorrie awarded new steel processing facility for Kloeckner Metals

The construction will take place on a 16-acre greenfield site at ThyssenKrupp Industrial Park in Calvert.

| Oct 30, 2012

Lord, Aeck & Sargent announces four student life facility wins

Projects recognize the architecture firm’s expertise on a nationwide basis.

| Oct 30, 2012

The Beck Group announces CEO succession plan

Current Eastern Division Director and company veteran, Fred Perpall, named CEO.

| Oct 30, 2012

Two-hour fire rated curtain wall passes CDC tests

CDC (Curtain Wall Design and Consulting) is an independent firm providing a wide range of building envelope design, engineering, and consulting services to design professionals nationwide.

| Oct 30, 2012

Wight & Company announces three hires

Expands team and adds staff to work on the UNO project.

| Oct 15, 2012

Silicones from Dow Corning solve high-altitude technical challenges at the world’s tallest tower

The spectacular Burj Khalifa skyscraper soars to 828m above ground level, holding the record for being the world’s tallest building and also for the highest installation of an aluminum and glass façade. To take on its numerous challenges and technical difficulties, it required proven silicone solutions and full support from Dow Corning.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021