Most top U.S. contractors rarely deliver projects on time: new study

Contractors

Most top U.S. contractors rarely deliver projects on time: new study

Struggles with supply chain disruptions, construction costs, and new sustainability requirements cause delays, according to a new study by XYZ Reality.


By Peter Fabris, Contributing Editor | June 26, 2023
Photo by Ricardo Gomez Angel on Unsplash
Photo by Ricardo Gomez Angel on Unsplash

About 63% of leading U.S. contractors are delivering projects out of schedule, according to a survey of over 300 C-suite executives and owners in the construction industry by XYZ Reality.

The study implies that the industry is struggling with significant backlogs due, in part, to avoidable defects, scan, and rework. The construction sector is also hampered by supply chain disruptions (cited by 52% of respondents), rising construction costs (43%), and meeting new sustainability requirements (36%).

Other reasons cited for falling short of schedule benchmarks include poor communication (45%), inexperienced workers (39%), and insufficient supervision (34%). This data suggests that a significant amount of human error is to blame, XYZ notes.

Design changes, or the misinterpretation of them, were also cited by about a quarter of respondents. To control costs and cope with industry challenges, contractors are increasingly looking to technology solutions such as augmented reality.

Related Stories

| Oct 4, 2012

Gilbane publishes Fall 2012 construction industry economic report

Report outlines fluctuation in construction spending; predicts continued movement toward recovery.

| Oct 3, 2012

Fifth public comment period now open for update to USGBC's LEED Green Building Program

LEED v4 drafts and the public comment tool are now available on the newly re-launched, re-envisioned USGBC.org website.

| Oct 2, 2012

Mirvish and Gehry unveil conceptual design to transform Toronto’s entertainment district

Reimagining of King Street Entertainment District supports Toronto’s cultural corridor.

| Oct 2, 2012

Dow Business Services Center building named 2012 “America’s Best Buildings of the Year” winner

Building constructed with air sealing and insulation products from Dow Building Solutions.

| Oct 2, 2012

Bernards working on project at L.A. White Memorial Medical Center

The new facility is a $15-million, 41,000-sf concrete structure which includes three stories of medical office space atop a three-level parking garage.

| Oct 1, 2012

Tyco completes separation process, now largest pure-play fire protection and security business

Tyco Integrated Security focused on delivering security solutions to commercial businesses.

| Sep 28, 2012

Seattle is home to first LEED-certified modular radiation center

By using modular construction and strategic site design, RAD Medical Systems built the first radiation center to receive LEED certification.

| Sep 26, 2012

EDITORIAL OPPORTUNITY – BD+C Greenbuild 2012 Issue

Your firm is invited to contribute to this special issue, which will be distributed at Greenbuild San Francisco, Nov. 14-16, 2012.

| Sep 24, 2012

Reed Construction completes Lafarge headquarters in Chicago

Reed Construction was contracted to complete the full third floor build-out which included the construction of new open area work space, private offices, four conference rooms with videoconferencing capabilities and an executive conference boardroom.

| Sep 24, 2012

Chicago Lakeside shortlisted for the Sustainia Award

The “Lakeside Idea” is about bridging a brownfield industrial past to a green lifestyle future, from steel mill to innovation mill.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021