Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Apr 18, 2018
New Green Globe pilot program launched
Precursor to revised Green Globes Assessment Protocol for Commercial Buildings.
Codes and Standards | Apr 17, 2018
Contractor charged with fraud in winning $200 million in federal contracts
Accused of falsely claiming veteran- and minority-owned business status.
Codes and Standards | Apr 16, 2018
Wide variations in adoption of National Electric Code could jeopardize safety
An NFPA report found that code adoption is under heavier political scrutiny, leading to delays and decisions motivated by factors other than safety concerns.
Codes and Standards | Apr 12, 2018
Corruption in New York City construction industry is common
Scale of projects, number of players involved contributes to problem.
Codes and Standards | Apr 11, 2018
Urgent need for government to make communities, infrastructure more resilient
More than 350 people died from extreme weather events in 2017.
Codes and Standards | Apr 10, 2018
Boosting energy efficiency helps reduce health risks
Cleaner air results in fewer heart attacks, respiratory disease, and premature deaths.
Codes and Standards | Apr 9, 2018
U.K. business leaders call for zero-carbon buildings by 2030
Real estate, construction industry executives among those supporting the goal.
Codes and Standards | Apr 5, 2018
In Houston, proposed rules would require building above 500-year flood level
Change would impact 85,739 pieces of property.
Codes and Standards | Apr 4, 2018
New ASTM standard supports stucco use in construction
Provides way to measure tensile strength in vertical applications.
Codes and Standards | Apr 3, 2018
LEED v4.1 O+M for Existing Buildings available for beta testing
Update said to be most inclusive and transparent platform to date.