Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Jun 28, 2018
Modular construction may be key to relieving housing crunch
May be only way to meet needs as ranks of construction workers decline.
Codes and Standards | Jun 27, 2018
Thirty nine San Francisco high rises at risk of collapse in major earthquake
Vulnerable buildings have welded columns and beams.
Codes and Standards | Jun 26, 2018
Boston enacts new climate resiliency rules for buildings
New policy is likely a first in the nation.
Codes and Standards | Jun 25, 2018
Integrated Project Delivery guide offered by Pankow Foundation
An Action Guide for Leaders offers answers to critical IPD questions.
Codes and Standards | Jun 21, 2018
New app said to automate code compliance
Startup offers plug-in that scans 3D models.
Codes and Standards | Jun 20, 2018
Home values and local tax revenues at risk from high tide flooding, scientists group says
Analysis of property data identifies communities prone to frequent flooding.
Codes and Standards | Jun 19, 2018
Structural engineered wood products exempt from new EPA formaldehyde ruling
Exempt products include structural plywood, oriented strand board (OSB).
Codes and Standards | Jun 18, 2018
Seattle City Council repeals controversial new per-worker tax on large employers
Measure was aimed at raising $50 million for homeless services, affordable housing.
Codes and Standards | Jun 14, 2018
Hardscape from development makes ‘1,000-year’ flood in Maryland worse
Impermeable concrete made it easier for water to overwhelm drainage system.
Codes and Standards | Jun 13, 2018
United States Resiliency Council announces support for Calif. earthquake resiliency bill
Measure would help cities identify structures that could fail in major quake.