Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Apr 2, 2018
Experts chosen for ICC, ANCR buildings resilience benchmarks project
Specialists to focus on community preparedness for disasters.
Codes and Standards | Mar 29, 2018
Contractors have paid $5.2 million for failing local resident employee mandate on Detroit arena
Companies were only able to meet half of the 51% local worker requirement over course of the project.
Codes and Standards | Mar 28, 2018
Washington State moving to promote mass timber construction with legislation
Bill would require all 12-story or less public buildings to be built with mass timber.
Codes and Standards | Mar 27, 2018
Los Angeles appoints its first chief design officer
Responsibility for enhancing civic architecture and urban design.
Codes and Standards | Mar 26, 2018
National Roofing Contractors Assn., releases updates to its Roof Wind Designer app
Significant changes to online wind-load calculator.
Codes and Standards | Mar 22, 2018
Global construction waste to almost double by 2025
Concerns in Houston, Minnesota over environmental impacts.
Codes and Standards | Mar 21, 2018
Cape Town, South Africa’s dire water supply crisis raises concerns in the U.S.
Los Angeles, Salt Lake City, and Miami among cities at risk for water shortages.
Codes and Standards | Mar 20, 2018
Report shows how LEED certification supports net zero energy
Whole-building energy simulation, ASHRAE compliance requirement are key factors.
Codes and Standards | Mar 15, 2018
Energy efficiency measures contributing to flat demand for power
Utilities having difficulty adjusting to new business environment.
Codes and Standards | Mar 14, 2018
New parking lighting technology is paying off, Energy Dept. says
Newer products can cut energy costs by as much as 70%.