Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets.


By David Barista, Editor-in-Chief | August 20, 2013
Many AEC firms that specialize in data centers report growth in the retrofit mar
Many AEC firms that specialize in data centers report growth in the retrofit market. An example is the 450,000-sf EMC Cloud Data Center in Durham, N.C., which was built in a former IBM warehouse. The buildings original exterior was kept in place, and its loading docks were repurposed as air-side economizers. Symmes Maini and McKee Associates led the design team. DPR Construction was the construction manager. PHOTO: ROBERT BENSON PHOTOGRAPHY

While the once white-hot data center construction market has cooled off in recent years, the outlook for this sector remains quite rosy. Each year, businesses and institutions spend billions on data center construction and retrofit projects to keep up with the nation’s insatiable demand for data storage and processing. 

The data center sector is conservatively estimated at $13-15 billion annually—larger than the hospitality, amusement/recreation, and water supply sectors, according to U.S. Census Bureau data. And the emergence of cloud computing and storage, combined with the “never delete anything” mindset of consumers and businesses, will only drive demand for data storage and processing.  

“The data center market should generally follow the growth of Internet traffic, and Internet traffic continues to grow strongly,” says Craig Deering, AIA, LEED AP, National Practice Leader – Critical Facilities with HDR Architecture.

According to a May 2013 report from Cisco Systems, IP traffic volume in North America is expected to grow to 40 exabytes a month by 2017, a 23% cumulative annual growth rate. Cisco predicts global IP traffic will increase threefold over the next five years. Driving this steep growth are the explosion of networked devices, especially wireless gadgets, and the emergence of video as a dominant content type. Cisco predicts that traffic from wireless and mobile devices will exceed wired devices by 2016, and video will reach 69% of global consumer Internet traffic by 2017.

TOP DATA CENTER ARCHITECTURE FIRMS

 
2012 Data Center Revenue ($)
1 Corgan $27,534,191
2 Gensler $23,330,000
3 HDR Architecture $16,295,000
4 Integrated Design Group $14,598,910
5 PageSoutherlandPage $14,450,000
6 Reynolds, Smith and Hills $4,360,000
7 Callison $3,973,699
8 Little $3,655,590
9 RTKL Associates $3,634,000
10 EwingCole $3,000,000

TOP DATA CENTER ENGINEERING FIRMS

 
2012 Data Center Revenue ($)
1 Fluor $235,678,900
2 Syska Hennessy Group $36,735,434
3 Jacobs Engineering Group $36,700,000
4 H&A Architects & Engineers $35,427,599
5 URS Corp. $26,229,049
6 Environmental Systems Design $10,575,892
7 Parsons Brinckerhoff $10,300,000
8 H.F. Lenz $7,357,000
9 Science Applications International Corp. $6,760,598
10 AKF Group $6,602,000

TOP DATA CENTER CONSTRUCTION FIRMS

 
2012 Data Center Revenue ($)
1 DPR Construction $895,882,459
2 Balfour Beatty $753,194,214
3 Holder Construction $710,000,000
4 Turner Corporation, The $501,750,000
5 Whiting-Turner Contracting Co., The $490,093,045
6 Mortenson Construction $307,360,000
7 Structure Tone $285,725,000
8 Skanska USA $236,396,858
9 Gilbane $130,362,000
10 Carlson Design Construct $128,000,000

Giants 300 coverage of Data Centers brought to you by System Sensor www.systemsensor.com

What does this mean in terms of construction spending growth? If the Data Center Dynamics annual census of the industry is any indication, the data center construction market will remain one of the fastest-growing sectors in the country. According to DCD Intelligence’s most recent survey of nearly 3,800 data center owner/operators and 1,600 vendors, data center facility investment was up 23% on the Coasts and 50% in the central U.S. in 2011-12.

“Calculating the size of the data center market is challenging,” says Deering, “but no matter how you look at it, there’s no doubt that the data center market stands on its own as a distinct and meaningful sector.”

Achieving a lower cost of computing

Shrinking IT budgets and rising operational costs have led data center operators and corporate clients to scrutinize project budgets. As a result, AEC firms are being tasked with finding solutions for lowering the overall cost of computing and operating and maintaining the facilities. 

This, in turn, is driving innovation in data center design, including the use of advanced cooling schemes, energy-efficient IT equipment, and higher-density environments. Advanced technologies like KyotoCooling, which utilizes heat wheels to reduce the cooling load on the building’s HVAC system, are becoming more common in U.S. data center projects. In addition, a growing number of data center operators are choosing to build new facilities in northern climates to take advantage of the cooler outdoor air temperatures.  

Advancements in server technology, combined with a recent change to ASHRAE’s TC 9.9 Datacom guidelines, means that Building Teams can deliver facilities that operate at higher internal temperatures, greatly reducing cooling costs.   

“The top end of the allowable range now is 80.6°F, up from 76°F previously,” says Ronald Vokoun, DBIA, LEED AP BD+C, Mission Critical Market Leader – Western Region with JE Dunn Construction. “Generally speaking, for every 1.8°F that you raise the temperature in your data center, you save 2-4% of your total energy bill. That’s a pretty high and immediate ROI.”

Rising costs are forcing many companies to outsource their data hosting through co-location and cloud services. This trend is leading to the construction of more mega-data center facilities, like CyrusOne’s new Chandler, Ariz., complex, which will eventually house more than 

1 million sf of data center space. By 2015, just 2% of the world’s data centers will contain 60% of the floor space, up from 52% in 2010, according to a report from Gartner Inc. 

“We will continue to see the concentration of data center floor space into a small community of dominant global players,” says HDR’s Deering.

Retrofits: A growth market

An emerging market for AEC firms is data center retrofits. The first wave of data centers—built during the dot-com boom of the late 1990s—are woefully outdated and are prime for retrofitting. Even the facilities built years later are behind the technology curve, and operators will be looking to upgrade their servers and infrastructure to meet the computing demands of today’s market.      

“Many companies are looking at the ‘capex’ versus ‘opex’ dollars and realizing that they can strike a meaningful balance between the two by simply updating, retrofitting, or renovating their existing facilities,” says Jerry Sumrell, PE, Vice President, Mission Critical with RS&H. “This presents new challenges to the design industry, as we will be devoting more time to working in live data center environments with all of the associated risks that come with it. It’s akin to performing open-heart surgery—you have to keep the facility running 24/7 while adding new equipment, decommissioning existing equipment, and transferring power/cooling from one piece of equipment to another.”

Read BD+C's full Giants 300 Report

Related Stories

| Nov 26, 2013

Design-build downsized: Applying the design-build method in an era of smaller projects

Any project can benefit from the collaborative spirit and cooperative relationships embodied by design-build. But is there a point of diminishing return where the design-build project delivery model just doesn't make sense for small projects? Design-build expert Lisa Cooley debates the issue.

| Nov 25, 2013

Insider tips on how to get picked a BD+C 40 Under 40 winner

We just posted the Entry Form for our 9th Annual BD+C "40 Under 40" competition. Frankly, the Entry Form is just the basic data. The real meat of your entry is your Personal Statement.

| Nov 25, 2013

Building Teams need to help owners avoid 'operational stray'

"Operational stray" occurs when a building’s MEP systems don’t work the way they should. Even the most well-designed and constructed building can stray from perfection—and that can cost the owner a ton in unnecessary utility costs. But help is on the way.

| Nov 25, 2013

Manufacturers race to offer EPDs, HPDs in response to LEED v4

Under LEED v4, projects are awarded points for using at least 20 building products that have issued Environmental Product Declarations or Health Product Declarations. In response, manufacturers are racing to offer EPDs and HPDs for their product lines. 

| Nov 25, 2013

Electronic plan review: Coming soon to a city near you?

With all the effort AEC professionals put into leveraging technology to communicate digitally on projects, it is a shame that there is often one major road block that becomes the paper in their otherwise “paperless” project: the local city planning and permitting department. 

| Nov 22, 2013

Health Product Declaration Collaborative to develop protocol for third-party verification of HPDs

Seven leading product sustainability assessment companies partner with the HPD Collaborative to develop the verification and quality assurance protocols.

| Nov 22, 2013

Kieran Timberlake, PE International develop BIM tool for green building life cycle assessment

Kieran Timberlake and PE International have developed Tally, an analysis tool to help BIM users keep better score of their projects’ complete environmental footprints.

Sponsored | | Nov 20, 2013

Four faces of curb appeal

The Furniture Row retail center in Charlotte, N.C., incorporates four specialty stores in a distinctive, efficient structure. 

| Nov 20, 2013

Architecture Billings Index slows in October; project inquiries stay strong

Following three months of accelerating demand for design services, the Architecture Billings Index reflected a somewhat slower pace of growth in October. The October ABI score was 51.6, down from a mark of 54.3 in September.

| Nov 19, 2013

Pediatric design in an adult hospital setting

Freestanding pediatric facilities have operational and physical characteristics that differ from those of adult facilities.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021