Memorial Field House, once the lovely Collegiate Gothic (ca. 1933) centerpiece (along with neighboring University Hall) of the University of Toledo campus, took its share of abuse after a new athletic arena made it redundant, in 1976. The ultimate insult occurred when the ROTC used it as a paintball venue.

All that changed in 2006, when the university, facing a burst in student enrollment, an expansion of program offerings, and concern about future space needs, commissioned a major overhaul that, three years later, recast the 134,200-sf gymnasium into a LEED Gold learning environment housing classrooms, teaching labs, faculty offices, and space for future growth.

The extensive Building Team, led by Cincinnati’s BHDP Architecture, literally constructed a building within a building, expanding the single-floor high-bay arena into three floors within the existing building envelope. The tri-level structure, with its exposed steel truss supports, features a dramatic cruciform skylight above a “Town Hall” atrium that has become one of the most popular meeting and study spaces on campus.

Planning for the project ensured that the university would have sufficient classroom space to meet its enrollment projections through 2020. Fifty-four classrooms, varying in size for classes of 20, 30, or 40, were built. A practice gym was converted into a 250-seat, three-screen auditorium; another was repurposed for language laboratories. The “Collegiate Loft” on the new third floor houses the UT Center for Teaching and Learning. The latest A/V equipment—flat panel monitors, electronic whiteboards, audience response systems—enables multiple teaching styles.

Memorial Field House was the university’s first LEED Gold building. Two noteworthy innovations: 1) the Building Team kept a chilled water plant housed in the building’s central courtyard fully operation, along with a 15kV electrical substation and main campus communications fiber; and 2) the team field erected new air-handling units in two old basketball gyms and integrated engineered smoke control with the new skylight system.

“They definitely did their homework,” said jurist Tom Brooks, VP of Reconstruction at Chicago’s Berglund Construction. “They maintained the façade, which is important to me, and did it all on a budget so low it almost looks like a typo.” For the record, construction costs were $21.5 million, or $160/sf. BD+C

PROJECT SUMMARY

Building Team

Owner: The University of Toledo

Submitting firm: BHDP Architecture (architect, interior designer)

Civil/structural engineer: Poggemeyer Design Group

MEP engineer: Heapy Engineering

Program analyst: Comprehensive Facilities Planning, Inc.

General contractor: A. Z. Shimina, Inc.

A/V, IT, acoustics consultant: The Sextant Group

Steel construction: Mosser Construction

Cost consultant: ProjDel Corp.

General Information

Area: 134,200 gsf

Construction cost: $21.5 million

Construction time: January 2006 to January 2009

Related Stories

| May 19, 2014

Why e-commerce won't kill 'bricks and mortar' retail sector

Despite emerging structural challenges and newly-announced store closings, such as those of Radio Shack and Office Depot, the U.S. retail sector has continued on its solid recovery.

| May 16, 2014

BoA, USGBC to offer $25,000 grants for green affordable housing projects

The Affordable Green Neighborhoods Grant Program will offer 14 grants to developers of affordable housing in North America who are committed to building sustainable communities through the LEED for Neighborhood Development program. 

| May 16, 2014

HED expands leadership in San Diego

Neville Willsmore, Thomas Christian join leadership team for Harley Ellis Devereaux.

| May 16, 2014

Toyo Ito leads petition to scrap Zaha Hadid's 2020 Olympic Stadium project

Ito and other Japanese architects cite excessive costs, massive size, and the project's potentially negative impact on surrounding public spaces as reasons for nixing Hadid's plan.  

| May 15, 2014

Paints, coatings, and sealants: 10 new ways to seal the deal

Color-shifting finishes, dry-erase surfaces, and stain-blocking paints are highlighted in this round up of new offerings in paints, coatings, sealants, and finishes. 

| May 15, 2014

Biking to work up by 60 percent, according to Census Bureau report

Many U.S. cities are seeing an increase in bicycle commuters, according to new a U.S. Census Bureau report. While bicyclists still account for just 0.6% of all commuters, some of the nation's largest cities have more than doubled their rates since 2000.

| May 15, 2014

'Virtually indestructible': Utah architect applies thin-shell dome concept for safer schools

At $94 a square foot and "virtually indestructible," some school districts in Utah are opting to build concrete dome schools in lieu of traditional structures. 

| May 15, 2014

First look: 9/11 Memorial Museum opens to first-responders, survivors, 9/11 families [slideshow]

The 110,000-sf museum is filled with monumental artifacts from the tragedy and exhibits that honor the lives of every victim of the 2001 and 1993 attacks. 

| May 14, 2014

New study shows employees aren't happier working in green buildings

People working in buildings certified under LEED’s green building standard appear no more satisfied with their workplace environments than those in conventional buildings, according to new research from the University of California, Berkeley, and the University of Nottingham.

| May 14, 2014

Construction growth looking up: Gilbane Spring 2014 Economic Report

Construction spending for 2014 should finish 6.6% higher than in 2013, with nonresidential work contributing substantially.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021