UNC Health Care’s Surgical Tower set to begin construction

Healthcare Facilities

UNC Health Care’s Surgical Tower set to begin construction

Skanska USA will build the project in three phases.


By David Malone, Associate Editor | November 5, 2019

All renderings courtesy UNC Health Care

Set to become the largest building on UNC Hospitals Chapel Hill campus, the new 335,000-sf Surgical Tower will enhance UNC Health Care’s ability to provide surgical and medical care for Carolina residents.

The seven-story tower will feature 24 operating rooms, two hybrid operating rooms, 56 pre- and post-operating rooms, and two floors of ICU space with 56 beds. The building will also include a basement level, a main reception and visitor waiting areas on each floor, offices and conference rooms, an indoor and outdoor staff lounge, and staff locker rooms. 

 

Surgical Tower aerial

 

Patient drop-off canopies at the Surgical Tower and the existing Children’s Hospital will also be built. Two overhead pedestrian bridges will connect existing parking decks and the Dental School building to the Surgical Tower. Finally, the project will include a three-story service connector, renovation work at the existing Ambulatory Patient Care Facility, and the expansion of the cafe in the existing part of the hospital.

 

Surgical Tower canopy

 

The project, which is being built by Skanska, will be constructed in three phases. Phase one will include site development work and the new connector basement construction, phase two will focus on deep foundation construction, and phase three will focus on the main Surgical Tower building work.

 

See Also: Design unveiled for the University of Maryland’s School of Public Policy building

 

Surgical Tower East Facade

 

Phase one’s site development will include extensive utility relocations, an upgraded storm and sanitary system, new chilled water and steam for the tower and adjacent buildings, and new electrical duct bank from a future generator plant.

The project is slated for completion in 2022.

 

Surgical Tower entry

 

Surgical Tower west facade

Related Stories

| Jan 31, 2012

Suffolk Construction to manage Lawrence & Memorial Hospital Cancer Center project in Waterford, Conn.

Leading construction management firm overseeing one of first healthcare projects in the country to utilize innovative IPD process.

| Jan 16, 2012

Suffolk completes construction on progressive operating suite

5,700 square-foot operating suite to be test bed for next generation of imaged-guided operating techniques.

| Jan 4, 2012

HDR to design North America’s first fully digital hospital

Humber River  is the first hospital in North America to fully integrate and automate all of its processes; everything is done digitally.

| Jan 3, 2012

VDK Architects merges with Harley Ellis Devereaux

Harley Ellis Devereaux will relocate the employees in its current Berkeley, Calif., office to the new Oakland office location effective January 3, 2012.

| Jan 3, 2012

New Chicago hospital prepared for pandemic, CBR terror threat

At a cost of $654 million, the 14-story, 830,000-sf medical center, designed by a Perkins+Will team led by design principal Ralph Johnson, FAIA, LEED AP, is distinguished in its ability to handle disasters. 

| Jan 3, 2012

BIM: not just for new buildings

Ohio State University Medical Center is converting 55 Medical Center buildings from AutoCAD to BIM to improve quality and speed of decision making related to facility use, renovations, maintenance, and more. 

| Dec 12, 2011

Skanska to expand and renovate hospital in Georgia for $103 Million

The expansion includes a four-story, 17,500 square meters clinical services building and a five-story, 15,700 square meters, medical office building. Skanska will also renovate the main hospital.

| Dec 1, 2011

Nauset Construction breaks ground on Massachusetts health care center

The $20 million project is scheduled to be completed by December 2012. 

| Nov 29, 2011

Report finds credit crunch accounts for 20% of nation’s stalled projects

Persistent financing crunch continues to plague design and construction sector.

| Nov 28, 2011

Nauset Construction completes addition for Franciscan Hospital for Children

The $6.5 million fast-track, urban design-build projectwas completed in just over 16 months in a highly sensitive, occupied and operational medical environment.

boombox1
boombox2
native1

More In Category


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


Healthcare Facilities

U.S. healthcare building sector trends and innovations for 2024-2025

As new medicines, treatment regimens, and clinical protocols radically alter the medical world, facilities and building environments in which they take form are similarly evolving rapidly. Innovations and trends related to products, materials, assemblies, and building systems for the U.S. healthcare building sector have opened new avenues for better care delivery. Discussions with leading healthcare architecture, engineering, and construction (AEC) firms and owners-operators offer insights into some of the most promising directions. This course is worth 1.0 AIA/HSW learning unit.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021