Set to become the largest building on UNC Hospitals Chapel Hill campus, the new 335,000-sf Surgical Tower will enhance UNC Health Care’s ability to provide surgical and medical care for Carolina residents.
The seven-story tower will feature 24 operating rooms, two hybrid operating rooms, 56 pre- and post-operating rooms, and two floors of ICU space with 56 beds. The building will also include a basement level, a main reception and visitor waiting areas on each floor, offices and conference rooms, an indoor and outdoor staff lounge, and staff locker rooms.
Patient drop-off canopies at the Surgical Tower and the existing Children’s Hospital will also be built. Two overhead pedestrian bridges will connect existing parking decks and the Dental School building to the Surgical Tower. Finally, the project will include a three-story service connector, renovation work at the existing Ambulatory Patient Care Facility, and the expansion of the cafe in the existing part of the hospital.
The project, which is being built by Skanska, will be constructed in three phases. Phase one will include site development work and the new connector basement construction, phase two will focus on deep foundation construction, and phase three will focus on the main Surgical Tower building work.
See Also: Design unveiled for the University of Maryland’s School of Public Policy building
Phase one’s site development will include extensive utility relocations, an upgraded storm and sanitary system, new chilled water and steam for the tower and adjacent buildings, and new electrical duct bank from a future generator plant.
The project is slated for completion in 2022.
Related Stories
| Feb 28, 2012
McCarthy completes second phase of San Diego’s Scripps Hospital
Representing the second phase of a four-phased, $41.3 million expansion and remodeling project, the new addition doubles the size of the existing emergency department and trauma center to encompass a combined 27,000 square feet of space.
| Feb 28, 2012
Griffin Electric completes Medical University of South Carolina project
The 210,000-sf complex is comprised of two buildings, and houses research, teaching and office areas, plus conference spaces for the University.
| Feb 22, 2012
CISCO recognizes Gilbane for quality construction, design, and safety
The project employed more than 2,000 tradespeople for a total of 2.1 million hours worked – all without a single lost-time accident.
| Feb 14, 2012
The Jackson Laboratory announces Gilbane Building Co. as program manager for Connecticut facility
Gilbane to manage program for new genomic medicine facility that will create 300 jobs in Connecticut.
| Feb 13, 2012
WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold
Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby.
| Feb 13, 2012
New medical city unveiled in Abu Dhabi
SOM’s design for the 838-bed, three-million-square foot complex creates a new standard for medical care in the region.
| Feb 10, 2012
Mortenson Construction research identifies healthcare industry and facility design trends
The 2012 Mortenson Construction Healthcare Industry Study includes insights and perspectives regarding government program concerns, the importance of lean operations, flexible facility design, project delivery trends, improving patient experience, and evidence-based design.
| Jan 31, 2012
Fusion Facilities: 8 reasons to consolidate multiple functions under one roof
‘Fusing’ multiple functions into a single building can make it greater than the sum of its parts. The first in a series on the design and construction of university facilities.
| Jan 31, 2012
Suffolk Construction to manage Lawrence & Memorial Hospital Cancer Center project in Waterford, Conn.
Leading construction management firm overseeing one of first healthcare projects in the country to utilize innovative IPD process.
| Jan 16, 2012
Suffolk completes construction on progressive operating suite
5,700 square-foot operating suite to be test bed for next generation of imaged-guided operating techniques.