flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Too many construction projects don’t meet owners’ expectations: KPMG report

Contractors

Too many construction projects don’t meet owners’ expectations: KPMG report

Causes for delays, overruns, and underperformance include project management talent shortages, distrust between owners and contractors, and the lack of fully integrated project management systems. 


By John Caulfield, Senior Editor | April 20, 2015
Too many construction projects still don’t meet owners’ expectations: KPMG report

KPMG International's Global Construction Survery 2015 reported that 53% of owners say they suffered one or more underperforming projects in the previous year. Image: Wikimedia Commons

Despite their planning and risk management efforts, owners are still finding that a sizable percentage of their projects are either failing or aren’t coming in anywhere near on time or on budget.

More than half—53%—of owners say they suffered one or more underperforming projects in the previous year, a number that rises to 61% for larger organizations, according to KPMG International’s ninth annual Global Construction Survey 2015, based on interviews with 109 senior leaders from private and public organizations around the world that conduct construction activity.

Only 31% of respondents’ projects over the past three years came in within 10% of their budgeted cost. And only one quarter of projects over that period came in within 10% of their original deadlines.

The owners imply that these failures, delays, and overruns are less the result of poor project oversight than of talent shortages and the lack of integration of project management information systems into these companies’ accounting and procurement software programs.

 

 

Most owners polled assert that their companies use formal screening, prioritizing, and approval processes for projects, including financial and risk analysis (84%). More than 80% of respondents state that the majority of their capital projects are planned. Thirty percent of respondents use a design-bid-build project delivery strategy, while 32% use engineer-procure-construct.

“All potential projects should be systematically identified, classified, screened, prioritized, evaluated and selected,” writes Jeff Shaw, Director-KPMG in South Africa. “This process must be supported by an appropriate budget allocation and monitoring process. Throughout the capital allocation process, alignment between strategic objectives and the capital project portfolio must be tested.”

The report notes, however, that owners are challenged finding qualified project management personnel. Forty-five percent of respondents say they struggle to attract qualified craft labor, planners and project management professionals. 

While 64% of respondents believe their management controls are either “optimized” or “monitored,” nearly one-third concede that their controls are “standardized,” with no testing or reporting or reporting to management and only limited staff training.

Most construction companies rely heavily on software to manage projects. Fifty-five percent of respondents say they are “satisfied” or “mostly satisfied” about the return on investment from project management tools and training. And 73% say they are confident about the accuracy and timeliness of reports they receive from managers and contractors. 

However, only about half of respondents say their organizations have introduced an integrated project management information system (PMIS). Consequently, less than one-fifth of respondents could answer “yes” definitively when asked if investments in project governance and controls have reduced project costs. 

In planning for delays and cost overruns, senior executives polled identify a range of methods to calculate contingency levels. The two most popular are setting aside an specific amount of contingency for all projects (e.g., 10%), and quantitative risk analysis. “The relative sophistication of the latter suggests that owners are trying to become more accurate in their forecasting,” the report states.

Sixty-nine percent of owners polled say that “poor contractor performance” is one of the biggest reasons for failing projects, delays, or cost overruns. And there’s definitely something negative going when only one-third could say they have a “high” level of trust with pros. 

More than eight in 10 respondents expect greater collaboration with contractors over the next five years. How much these relationships actually change, though,  remains to be seen. The report suggests that lump-sum, fixed-price contracts, which dominate among the survey’s respondents, are one reason for the fragile state of owner-contractor relationships, primarily because they defer risk onto the contractor. And owners believe the balance of power is shifting toward them; nearly half expect to have more negotiating strength when delivering capital projects over the next five years.

KPMG International offers five steps for owners to improve the performance of their projects:

  • Take a fresh approach to talent management through more effective recruitment, development, and retention strategies;
  • Execute a fully integrated PMIS for swift coordination and real-time reporting;
  • Demand practical targets from contractors based on realistic expectations of what can go wrong;
  • Use contingency planning to control costs rather than excuse overruns; and
  • Invest in relationships with contractors by creating integrated project teams. 

Related Stories

| Apr 29, 2014

Best of Canada: 12 projects nab nation's top architectural prize [slideshow]

The conversion of a Mies van der Rohe-designed gas station and North Vancouver City Hall are among the recently completed projects to win the 2014 Governor General's Medal in Architecture. 

| Apr 29, 2014

USGBC launches real-time green building data dashboard

The online data visualization resource highlights green building data for each state and Washington, D.C.

| Apr 28, 2014

Welcome to the Hive: OVA designs wild shipping container hotel for competition

Hong Kong-based OVA envisions a shipping-container hotel, where rooms could be removed at will and designed by advertisers.

Smart Buildings | Apr 28, 2014

Cities Alive: Arup report examines latest trends in urban green spaces

From vertical farming to glowing trees (yes, glowing trees), Arup engineers imagine the future of green infrastructure in cities across the world.

| Apr 25, 2014

A radiant barrier FAQ: Everything you wanted to know but were afraid to ask

There are many examples of materials developed for the space program making their way into everyday life and radiant barriers are just that. SPONSORED CONTENT

| Apr 24, 2014

Unbuilt and Famous: LEGO releases box set of Bjarke Ingels' LEGO museum

LEGO Architecture has created a box set that customers can use to build replicas of the LEGO Museum, which is not yet built in real life. The museum, designed by the Bjarke Ingels Group, will commemorate the history of LEGO.

| Apr 23, 2014

Ahead of the crowd: How architects can utilize crowdsourcing for project planning

Advanced methods of data collection, applied both prior to design and after opening, are bringing a new focus to the entire planning process.

| Apr 23, 2014

Developers change gears at Atlantic Yards after high-rise modular proves difficult

At 32 stories, the B2 residential tower at Atlantic Yards has been widely lauded as a bellwether for modular construction. But only five floors have been completed in 18 months.

| Apr 23, 2014

Experimental bot transfers CAD plans onto construction sites

The Archibot is intended to take technical data and translate it into full-scale physical markings on construction sites.

| Apr 23, 2014

Mean and Green: Top 10 green building projects for 2014 [slideshow]

The American Institute of Architects' Committee on the Environment has selected the top ten examples of sustainable architecture and ecological design projects that protect and enhance the environment. Projects range from a project for Portland's homeless to public parks to a LEED Platinum campus center.

boombox1
boombox2
native1

More In Category

Student Housing

The University of Michigan addresses a decades-long student housing shortage with a new housing-dining facility

The University of Michigan has faced a decades-long shortage of on-campus student housing. In a couple of years, the situation should significantly improve with the addition of a new residential community on Central Campus in Ann Arbor, Mich. The University of Michigan has engaged American Campus Communities in a public-private partnership to lead the development of the environmentally sustainable living-learning student community.



Adaptive Reuse

Empty mall to be converted to UCLA Research Park

UCLA recently acquired a former mall that it will convert into the UCLA Research Park that will house the California Institute for Immunology and Immunotherapy at UCLA and the UCLA Center for Quantum Science and Engineering, as well as programs across other disciplines. The 700,000-sf property, formerly the Westside Pavilion shopping mall, is two miles from the university’s main Westwood campus. Google, which previously leased part of the property, helped enable and support UCLA’s acquisition.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021