Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Dec 23, 2015

International Code Council approves updates based on NIST study of Joplin, Mo. tornado

Applies to schools and other high occupancy buildings.

Codes and Standards | Dec 21, 2015

Changing building codes to protect against mass shootings at odds with other safety measures

Fire and other emergencies require getting people out quickly, not locking down sections.  

Codes and Standards | Dec 18, 2015

Codes should be updated to reflect lessons learned from recent extreme weather events

More can be done to boost resiliency to flooding, extended power outages.

Codes and Standards | Dec 1, 2015

More than 50 design, construction, and real estate firms urge action on climate change

Call for policymakers to move on one of the ‘greatest economic opportunities of the 21st Century’

Codes and Standards | Oct 26, 2015

Chicago suburb considers bird collision deterrent requirement on all new buildings

The rule would mandate that new commercial, multifamily structures comply with LEED pilot program.

Codes and Standards | Oct 16, 2015

Anchorage may raise building height restrictions that would block precious winter sunlight

Controversial measure is part of plan to spur development.

Codes and Standards | Oct 9, 2015

New California law means commercial building benchmarking program will be implemented

Multifamily housing to be included, a first for a U.S. state.

Codes and Standards | Oct 2, 2015

New ASHRAE guideline for commissioning existing systems and assemblies

Focuses on optimum facility and system operation.

boombox1
boombox2
native1

More In Category


Resiliency

U.S. is reducing floodplain development in most areas

The perception that the U.S. has not been able to curb development in flood-prone areas is mostly inaccurate, according to new research from climate adaptation experts. A national survey of floodplain development between 2001 and 2019 found that fewer structures were built in floodplains than might be expected if cities were building at random.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021