Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Codes and Standards

Supply chain constraints, shifting consumer demands adding cost pressures to office fit-outs

Contractors expect continuing increases in material lead time, project timelines this year.
 


By Peter Fabris, Contributing Editor | April 25, 2022
Office fit out
Courtesy Pexels.

Cushman & Wakefield’s 2022 Americas Office Fit-Out Cost Guide found supply chain constraints and shifting consumer demands will continue to add pressure to costs, both in materials and labor.
 
Increases in construction and customer demand for durable and non-durable goods have driven supply chain disruptions over the past two years. COVID-19 outbreaks and labor shortages have also wreaked havoc through ports and on trucking, transportation, and distribution capacities. The supply chain stress indices for both China and the U.S. ended 2021 up over 40% from pre-pandemic levels.
 
For office construction and fit-outs, these stressors have created increased delays, greater uncertainty, and higher costs. There appears to be some light at the end of the tunnel, though,
as the supplier delivery index that measures manufacturer delays has been receding
since the middle of 2021, the report says.
 
The waning of the pandemic may add more fuel to cost pressures, however, as office tenants are targeting the first half of 2022 for employees to return to a more standard office attendance model. “As office space usage increases, we expect organizations will expand their piloting and testing of different types of layouts related to hybrid work,” the report says. “This is likely to increase the amount of fit-out and office space construction activity in the coming quarters, creating even more demand for materials and labor.”

Related Stories

Codes and Standards | Apr 26, 2017

Chicago commits to 100% renewable power for all city buildings

In doing so, it becomes largest U.S. city to make such a pledge.

Codes and Standards | Apr 25, 2017

Concerns over increased construction costs following Trump executive orders

‘Buy American’ requirement and revised H-1B visa restrictions could raise prices on supplies, labor.

Codes and Standards | Apr 24, 2017

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.

Codes and Standards | Apr 20, 2017

California lawmakers have had little success in attracting sports stadiums

Only one of several attempts has had an impact in recent years.

Codes and Standards | Apr 19, 2017

Dept. of Energy releases updated versions of EnergyPlus and OpenStudio building energy modeling tools

The updated versions include full support for variable speed DX coils, enhanced plant auto-sizing, new fan model, and support for non-rectangular windows.

Codes and Standards | Apr 18, 2017

K-12 school daylighting initiative created to promote best practices

Eneref Institute creates networking group of school administrators for ideas to overcome market obstacles.

Codes and Standards | Apr 17, 2017

OSHA delays enforcing crystalline silica standard in construction industry

Enforcement will begin Sept. 23, three months later than planned. 

Codes and Standards | Apr 13, 2017

Former OSHA official publishes safety citations on his own

Under Trump orders, agency had stopped issuing ‘shaming’ press releases on major fines and safety violations.

Codes and Standards | Apr 12, 2017

Trump infrastructure task force suggests arbitration to speed projects

Permitting process could be reduced from 10 years to 2 years under the proposal.

Codes and Standards | Apr 11, 2017

2017 National Energy Codes Conference includes code boot camp, PNC Tower tour

The DOE-sponsored event will be held in Pittsburgh July 17-20.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021