A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.
These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.
The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).
The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.
Related Stories
Codes and Standards | Jan 11, 2021
Zero Energy Buildings growth driven by government policy, stringent codes, technologies
Restraints include high upfront cost, and lack of universal definition and approaches.
Codes and Standards | Jan 11, 2021
HUD releases new Fair Housing Act design and construction requirements
First update of ‘safe harbors’ in 15 years provides better clarity for design and construction firms.
Codes and Standards | Jan 8, 2021
Court ruling gives UpCodes upper hand in fight over building codes database
Battle over IP property claims by ICC and other codes bodies continues.
Codes and Standards | Jan 8, 2021
Houston creates tax incentives for green stormwater elements
Businesses that install green roofs, rain gardens, permeable pavement, and rainwater harvesting are eligible.
Codes and Standards | Jan 7, 2021
Trump’s classical design aesthetic mandate for federal buildings likely to be felt for years
May limit the number of firms that could compete for contracts.
Codes and Standards | Jan 7, 2021
Workers on some of Virginia’s major construction projects sue subcontractors for wage theft
Projects include new General Assembly Building, outpatient facility at Virginia Commonwealth University.
Codes and Standards | Jan 5, 2021
EPA finalizes first major update to Lead and Copper rule
Will accelerate pace of lead service line replacement.
Codes and Standards | Jan 5, 2021
Flood risk for affordable housing expected to triple by 2050
Some communities will have 90% of their affordable housing at risk.
Codes and Standards | Jan 4, 2021
Ranks of remote workers expected to double in five years
Nearly 23% of employees will work from outside of offices.
Codes and Standards | Dec 28, 2020
CSI and ASTM standards can now be connected through a central location
CROSSWALK web service accesses standards specific to projects from feasibility to turnover.