‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Oct 26, 2021

Drownings during Hurricane Ida point out FEMA flood map flaws

Eleven people drowned in New York City in areas marked as low risk.

Codes and Standards | Oct 20, 2021

New York City passes overhaul of construction codes

Over 600 major changes along with thousands of smaller updates slated for 2022.

Codes and Standards | Oct 20, 2021

One-quarter of U.S. critical infrastructure at risk of failure due to flooding

Police and fire stations, hospitals, airports, and wastewater treatment facilities face threat.

Codes and Standards | Oct 19, 2021

Pittsburgh enacts first-in-the-nation “Dark Sky Lighting” law

Applies to all city parks, facilities, and streetlights.

Codes and Standards | Oct 15, 2021

New Calif. law mandates use of lead-free plumbing fixtures

Must meet NSF/ANSI/CAN 61-2020 in 2023.

Codes and Standards | Oct 14, 2021

Building industry leaders urge governments to boost emissions reductions targets

Scores of large AEC firms and organizations sign letter to UN’s COP 26 group.

Codes and Standards | Oct 13, 2021

FEMA’s new flood insurance plan will sharply raise insurance costs for seaside properties

Risk Rating 2.0 will have more accurate assessment of flood risk.

Codes and Standards | Oct 12, 2021

Three new laws expected to spur more affordable housing in California

Trio of measures could aid carbon reduction in built environment.

Codes and Standards | Oct 11, 2021

New program to promote mass timber construction launched in Boston

City’s planning and development agency to award grants for projects in early-stage planning.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021