A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.
These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.
The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).
The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.
Related Stories
Codes and Standards | Nov 12, 2021
GSA will likely shrink federal office space post-COVID
Agency also needs to address maintenance backlog.
Codes and Standards | Nov 10, 2021
Los Angeles launches fast-track office tenant improvements program
Red tape to be cut to make interiors healthier and safer.
Codes and Standards | Nov 9, 2021
Florida state building professionals call for mandatory high-rise building inspections
Group recommendation comes in wake of Surfside condo collapse.
Codes and Standards | Nov 8, 2021
Dept. of Energy to fund 10 pilot smart building projects
Connected communities will accelerate renewable energy adoption and grid resilience.
Codes and Standards | Nov 3, 2021
Fact sheets offer strategies to improve indoor air quality in schools
Center for Green Schools at USGBC document for people without a technical background.
Codes and Standards | Nov 2, 2021
Rapid acceleration of affordable housing development expected over next five years
Federal government programs will spur construction.
Codes and Standards | Nov 1, 2021
New bird-friendly technical design guide released
National Glass Assn. document offers design and installation best practices for glazing.
Codes and Standards | Nov 1, 2021
World’s first chief heat officer tackles how to protect Miamians from extreme heat
Focus on chronic exposure for outdoor workers and for those that can’t afford AC.
Codes and Standards | Oct 28, 2021
Design competition launched to show role of mass timber in decarbonization
Forest Service and Softwood Lumber Board will award $2 million in grants to winning teams.
Codes and Standards | Oct 27, 2021
Texas reforms series of contractor laws
Measures seen as making it easier to do business in the state.