‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

| Sep 11, 2013

White paper examines Joint Commission requirements for NFPA codes in healthcare

The healthcare industry has experienced great attention from The Joint Commission concerning fire and life safety issues.

| Sep 11, 2013

San Francisco expected to drop firefighter air tank refilling station rule for skyscrapers

San Francisco is poised to drop a requirement that skyscrapers have refill stations so firefighters can recharge their air tanks during a blaze. The city has required that new high-rises have the air refill systems for about ten years. 

| Sep 5, 2013

State legislatures continue to raise the bar on green school construction

Since the beginning of 2013, the USGBC has followed more than 125 bills across 34 states that seek to advance healthy, high-performing schools.

| Sep 5, 2013

Construction industry groups create coalition to respond to new OSHA silica rule

A group of 11 construction trade associations has created the Construction Industry Safety Coalition in response to the Occupational Safety and Health Administration’s (OSHA) proposed rule on silica for the construction industry.

| Sep 5, 2013

Red tape delays California county jail construction projects

California authorized $1.2 billion for jail construction in 2007, but not a single county in the state has completed a jail project since then.

| Sep 5, 2013

New CM-at-risk and design-build options create controversy in Ohio

Some contractors say Ohio's new system puts small and midsize construction companies at a disadvantage.

| Sep 5, 2013

Outdated codes slowed disaster recovery in Tuscaloosa, Ala.

Outdated building codes and lack of a master plan slowed the initial rebuilding stage after a devastating tornado leveled parts of Tuscaloosa, Ala. in 2011, according to the city’s mayor.

| Aug 28, 2013

Building collapse prompts legislation to beef up demolition regulations in Philadelphia

Philadelphia City Council will introduce legislation next month to strengthen the regulation of building demolition practices.

| Aug 28, 2013

Rules requiring contractors to boost hiring of veterans criticized

Some businesses are pushing back against proposed rules requiring federal contractors to step up their hiring of returning military service personnel.

| Aug 28, 2013

OSHA moves to reduced exposure to crystalline silica

Under a proposal from the Occupational Safety and Health Administration, the new permissible exposure limit to crystalline silica per cubic meter of air could be changed from 250 micrograms to 50 micrograms.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021