‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

| Sep 26, 2013

EPA’s final rule on updated ASTM standard likely to be withdrawn

The Environmental Protection Agency is expected to withdraw a direct final ruleissued in Augustregarding an ASTM standard for Phase I Environmental Site.

| Sep 26, 2013

A primer on RoofPoint green-rating system for commercial roofs

The RoofPoint green-rating system can be used to construct more energy-efficient and sustainable commercial roofs.

| Sep 26, 2013

ConsensusDocs releases updated federal subcontract to help construction firms perform federal work

The newly revised ConsensusDocs standard subcontract (ConsensusDocs 752 for federal work) will make it easier for general contractors and subcontractors to perform federal work.

| Sep 18, 2013

Proposed Boston casino development approval will depend partly on sustainability

The movement toward green building has been slow to catch on in the casino industry, but that could change with Suffolk Downs, which plans to build a $1 billion casino in Boston.

| Sep 18, 2013

Regulations could ease firefighters’ fear of roof solar panels

The local fire chief says solar panels are partly to blame after a 300,000 sf refrigerated warehouse in Delanco, N.J., burned down.

| Sep 18, 2013

New AISC design guide on structural stainless steel now available

For the first time in the U.S., design professionals now have an authoritative resource on structural stainless steel with AISC Steel Design Guide No. 27, Structural Stainless Steel.

| Sep 18, 2013

DBIA’s ‘Design-Build Done Right’ best practices project seeks industry input

The Design-Build Institute of America (DBIA) is seeking industry input on its project to create a design-build best practices document.

| Sep 11, 2013

USGBC Florida Chapter survey to help contractors adopt sustainable practices

Contractors in Florida could benefit from a data collection project by the state's chapter of the U.S. Green Building Council.

| Sep 11, 2013

Disability, vet hiring standards for contractors are goals, not quotas

Contractors that fall short of new federal hiring rules concerning veterans and disabled persons will not necessarily incur penalties, says Patricia Shiu, director of the Office of Federal Contract Compliance Programs.

| Sep 11, 2013

Sports stadium accidents suggest code updates may be necessary to prevent falls

Since 2000, at least three individuals have died as a result of falling from the upper decks of stadiums in the United States. In addition, eight non-fatal falls have occurred in stadiums and arenas over that time.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021