‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Resiliency | Jan 13, 2016

LEED credits on resiliency expected to influence future of building design

Post-disaster survivability is a key goal.

Codes and Standards | Jan 12, 2016

Batteries are the next step in raising sustainability standards

Battery technology will reduce electricity costs and promote a more stable, flexible grid.

Codes and Standards | Jan 4, 2016

Denver broadens its use of design reviews as construction booms

Support strong, but some wary of giving more say to review boards.  

Codes and Standards | Dec 23, 2015

International Code Council approves updates based on NIST study of Joplin, Mo. tornado

Applies to schools and other high occupancy buildings.

Codes and Standards | Dec 21, 2015

Changing building codes to protect against mass shootings at odds with other safety measures

Fire and other emergencies require getting people out quickly, not locking down sections.  

Codes and Standards | Dec 18, 2015

Codes should be updated to reflect lessons learned from recent extreme weather events

More can be done to boost resiliency to flooding, extended power outages.

Codes and Standards | Dec 1, 2015

More than 50 design, construction, and real estate firms urge action on climate change

Call for policymakers to move on one of the ‘greatest economic opportunities of the 21st Century’

Codes and Standards | Oct 26, 2015

Chicago suburb considers bird collision deterrent requirement on all new buildings

The rule would mandate that new commercial, multifamily structures comply with LEED pilot program.

Codes and Standards | Oct 16, 2015

Anchorage may raise building height restrictions that would block precious winter sunlight

Controversial measure is part of plan to spur development.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021