‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Apr 18, 2016

ASHRAE releases proposed energy standard for historic buildings

Designed to balance with preservation requirements.  

Codes and Standards | Apr 13, 2016

Canadian city fines itself for failing to get a building permit for building renovation

Guelph, Ontario, will pay a $1,125 fine to the province.

Codes and Standards | Apr 12, 2016

Construction trade groups sue OSHA over silica rule

Cite concerns about technological and economic feasibility.

Wood | Apr 8, 2016

New LEED Pilot ACP designed to help eliminate irresponsibly sourced materials

Illegal wood is primary target to restrict illicit material in the supply chain.  

Lighting | Apr 5, 2016

Lighting requirements for high-rise dwellings proposed for energy standard

The requirements would effectively eliminate incandescent and halogen bulbs.

Steel Buildings | Apr 4, 2016

AISI publishes Cold-Formed Steel Framing Design Guide, 2016 Edition

Updates 2007 edition; includes five comprehensive design examples.  

Data Centers | Apr 1, 2016

ASHRAE releases publication on the impact of IT equipment on data center design

The book offers advice for designing structures in the fast-changing data center industry.

Codes and Standards | Mar 28, 2016

Occupant egress simulations that impact codes fall short, researchers say

Building evacuations in emergencies are too dangerous as a result.  

School Construction | Mar 28, 2016

National report on school buildings reports $46 billion annual funding shortfall

Millions of students said to be learning in obsolete facilities.  

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021