‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Jun 21, 2017

World Green Building Council: All buildings must be net zero by 2050 to avert 2°C rise

Building efficiency essential to tempering global climate change.

Codes and Standards | Jun 21, 2017

Senate bill would prohibit tax money for sports stadium projects

Bipartisan legislation would prevent use of municipal bonds by pro teams.

Codes and Standards | Jun 19, 2017

Developer, architect hit with $10 million construction defect verdict

Case pertained to construction of condo development that was not fire code-compliant.

Codes and Standards | Jun 15, 2017

Cornell Tech unveils plans to reach Net Zero at The Bloomberg Center

Campus plans include photovoltaic arrays and geothermal ground source heat pumps.

Codes and Standards | Jun 13, 2017

Canada Green Building Council and Green Business Certification Inc. announce partnership

New joint venture will deliver enhanced services and support tools and programs throughout Canada.

Codes and Standards | Jun 8, 2017

Nail-Laminated Timber Design and Construction Guide released

New document focuses on design and construction considerations for horizontal NLT applications.

Codes and Standards | Jun 8, 2017

Car sharing popularity means parking zoning and codes may be promoting overbuilding of garages

Some designers look to modular designs in anticipation of alternate uses.

Codes and Standards | Jun 7, 2017

IAPMO advances toward new 2017 Water Efficiency and Sanitation Standard

Revised pipe-sizing method for residential applications will be included.

Codes and Standards | Jun 7, 2017

New Colorado law could stimulate stalled condo market

Construction defect law modifications could ease litigation risk and cut insurance rates.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021