‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Nov 15, 2018

New versions of DOE’s EnergyPlus engine and the OpenStudio software development kit released

New offerings resolve over 70 bugs and offer new features.

Codes and Standards | Nov 14, 2018

Obsolete safety standards may have been used in cleanup of former naval shipyard

San Francisco redevelopment site work may have been racked by fraud.

Codes and Standards | Nov 13, 2018

New York City’s new construction safety requirements are delayed

Some contractors say they weren’t ready for ‘massive initiative’.

Codes and Standards | Nov 9, 2018

Cities have multiple strategies to reduce parking requirements

Each community has to find its own mix of solutions.

Codes and Standards | Nov 8, 2018

Denver replaces green roof mandate with cool roof option

Less costly light-colored roofs can cut project costs by about 1.5%.

Codes and Standards | Nov 7, 2018

New report addresses sound transmission of wood-framed assemblies

AWC document provides empirical sound transmission model.

Codes and Standards | Nov 6, 2018

AIA releases 13 new and updated contract documents

Includes new Contractor-Subcontractor Master Agreement.

Codes and Standards | Nov 1, 2018

Several barriers holding back widespread construction of zero energy buildings

Code improvements and voluntary programs could add momentum.

Codes and Standards | Oct 31, 2018

Boston’s new flood protection plan centers on new parks

Initiative would add 67 acres of public open space.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021