‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Codes and Standards

‘Staggering delays, exorbitant costs’ in New York City library, cultural building construction

Study finds significant problems with how city manages capital projects.


By Peter Fabris, Contributing Editor | April 24, 2017

PIxabay Public Domain

A new report released by the Center for an Urban Future found significant flaws in how New York City manages capital projects for libraries and cultural institutions.

These projects encounter “staggering delays and exorbitant costs” the report says. The median new library and cultural project takes about seven years to complete and costs $930 per square foot, or roughly twice the cost of building a new office tower in the city, the report says.

The report, a joint project with the Citizens Budget Commission, analyzed 144 capital projects for libraries and cultural organizations completed between fiscal years 2010 and 2014. All were managed by the city’s Department of Design and Construction (DDC).

The report found that even seemingly routine maintenance projects end up taking years. For instance, the median mechanical system upgrade—including replacement and installation of fire alarms, boilers, and heating/cooling systems—took 4.3 years to complete. The study also found that when institutions are granted permission to self-manage capital projects, which is allowed on rare occasions, the projects typically take a fraction of the time and cost roughly 40% less.

Related Stories

Codes and Standards | Jan 9, 2019

Policymakers need to act to alleviate affordable housing crunch

Moody’s economist says costs including mortgage rates worsening situation.

Codes and Standards | Jan 7, 2019

Program uses low-cost sensors to monitor impact of stormwater mitigation systems

University/municipal partnership in Philadelphia aims to improve green infrastructure design.

Codes and Standards | Jan 7, 2019

Washington, D.C., to transition to 100% renewable energy by 2032

Includes measures to reduce emissions from buildings and transportation.

Codes and Standards | Jan 4, 2019

Canada’s National Building Code will include climate change obligations

New durability requirements for new buildings in the works.

Codes and Standards | Jan 4, 2019

LEED v4.1 beta registration begins in January

First releases are O+M, BD+C, and ID+C.

Codes and Standards | Jan 3, 2019

U.S. Appeals Court says general contractors can be cited for subcontractor violations

Ruling will prompt review of OSH decision that said GCs cannot be held liable for subs’ violations.

Codes and Standards | Jan 3, 2019

Tall mass timber code changes receive final approval

New provisions to be included in the 2021 International Building Code.

Codes and Standards | Jan 2, 2019

ASHRAE’s Low-Rise Residential Buildings standard update now available

Performance measures are at least 50% more efficient than 2006 IECC.

Codes and Standards | Jan 2, 2019

Study compares labor hours for various low-slope roofing options

Type of roof covering, project parameters, tool management, and crew efficiency all impact profitability.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021