flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Removable flood prevention system installed in one of New York City's largest office buildings

Removable flood prevention system installed in one of New York City's largest office buildings

55 Water Street is a virtual city unto itself, with enough excess power to support tenants for multiple days 


By Plaza Construction | March 31, 2014
Directly following Hurricane Sandy in October 2012, Plaza Construction was asked to start working on the development of a flood prevention solution for 55 Water Street, one of New York City’s largest office structures with 54 stories and 3.8 million square feet located in the financial district.  Hurricane Sandy was the second-costliest storm in U.S. history, with damages to New York City estimated at $50 billion due to storm surges flooding streets, tunnels and subway lines and cutting power in and around the city.
 
Plaza Construction, with a team of experts consisting of EKO Flood USA, architect HLW International, and engineer Thornton Tomasetti, along with New Water Street Corporation, the owner/operator of 55 Water Street managed the planning, design and permitting stages to produce the first permitted flood protection system for 55 Water Street. 
 
The new flood barrier protection system installed at 55 Water Street is designed to protect against an eight-foot flood line, higher than the 7-1/2 foot flood line recommended by FEMA to protect against storm surges for the next hundred years. The building was designed by renowned architect Emory Roth and the flood barrier protection system had to fit with the aesthetics of the building. Basically, it had to be invisible to the occupants and visitors of the building.
 
“Plaza was contracted by New Water Street Corporation to help them develop a flood protection system to guard against future storm surges that continue to be a major threat to the infrastructure of New York City and its neighboring communities,” said Richard Wood, CEO, Plaza Construction.  “Together with our partners, we created a simple, fast and easy solution in a modular set up, take down and store removable barrier flood protection system that is tested to withstand an 8-foot flood line.”
 
“The new flood protection system at 55 Water Street is designed to protect the entire building from flooding,” said George Acero, Executive Vice President, New Water Street Corporation. “For efficient preparedness, the building management plans to conduct drills on erecting and breaking down the system on an annual basis.”
 
The flood barrier system at 55 Water Street is based on a removable post and panel flood protection system that easily adapts to the requirements of a particular building site. The system at 55 Water Street is stored in the sub-level of the building and will require 30 men and eight hours to assemble into place, and completely protects the entire building against an 8-foot water line, preventing water from entering the building and seeping into the lower levels.
 
“The advanced design of the EKO system is new to the tri-state region, as we were presenting a unique concept for storm protection,” said Yu-chi Yang, the Project Architect at HLW International. “The final design resulted in a very comprehensive set of guidelines for reviewing similar proposals in the future.”
 
According to the Aine Brazil, Vice Chairman at Thornton Tomasetti, “The integration of the flood barrier system with the existing foundation wall was one key to the economic and practical feasibility, minimizing new foundations in the sidewalk, and providing the necessary continuity of the flood proofed bathtub as an extension of the existing 60 foot deep basement.”
 
Located in downtown Manhattan, 55 Water Street is a virtual city unto itself that provides a fail-safe operating environment. Powerful systems support massive capacities instilling confidence that any crisis can be readily addressed. An extraordinarily advanced technological infrastructure includes multiple redundancies in every major operating system from electric, HVAC, and telecom to life safety and security. Tenants can also avail themselves of sufficient excess power to operate without interruption for multiple days should an emergency situation arise. 
 
“Now with the installation of a removable, flood barrier protection system, 55 Water Street offers added protection in terms of guarding the building against flooding,” adds Mr. Acero.

Related Stories

Energy-Efficient Design | Apr 19, 2022

A prefab second skin can make old apartments net zero

A German startup is offering a new way for old buildings to potentially reach net-zero status: adding a prefabricated second skin.

Concrete Technology | Apr 19, 2022

SGH’s Applied Science & Research Center achieves ISO 17025 accreditation for concrete testing procedures

Simpson Gumpertz & Heger’s (SGH) Applied Science & Research Center recently received ISO/IEC17025 accreditation from the American Association for Laboratory Accreditation (A2LA) for several concrete testing methods.

Senior Living Design | Apr 19, 2022

Affordable housing for L.A. veterans and low-income seniors built on former parking lot site

The Howard and Irene Levine Senior Community, designed by KFA Architecture for Mercy Housing of California, provides badly needed housing for Los Angeles veterans and low-income seniors

Sponsored | BD+C University Course | Apr 19, 2022

Multi-story building systems and selection criteria

This course outlines the attributes, functions, benefits, limits, and acoustic qualities of composite deck slabs. It reviews the three primary types of composite systems that represent the full range of long-span composite floor systems and examines the criteria for their selection, design, and engineering.

Building Team | Apr 18, 2022

Shive-Hattery Acquires WSM Architects

Shive-Hattery announces that it has acquired WSM Architects, Inc., a 13-person architecture firm in Tucson, Arizona. 

University Buildings | Apr 18, 2022

SmithGroup to design new Univ. of Colorado Denver engineering, design, computing building

The University of Colorado Denver selected SmithGroup to design a new engineering, design, and computing building that will serve as anchor of new downtown innovation district.

Building Team | Apr 15, 2022

Frank Gehry to design his largest building yet for his hometown of Toronto

Famed architect Frank Gehry will design his largest building to date for his hometown of Toronto, Canada.

Healthcare Facilities | Apr 14, 2022

Healthcare construction veteran creates next-level IPD process for hospital projects

Can integrated project delivery work without incentives for building team members? Denton Wilson thinks so.

Industrial Facilities | Apr 14, 2022

JLL's take on the race for industrial space

In the previous decade, the inventory of industrial space couldn’t keep up with demand that was driven by the dual surges of the coronavirus and online shopping. Vacancies declined and rents rose. JLL has just published a research report on this sector called “The Race for Industrial Space.” Mehtab Randhawa, JLL’s Americas Head of Industrial Research, shares the highlights of a new report on the industrial sector's growth.

High-rise Construction | Apr 14, 2022

Seattle’s high-rise convention center nears completion

The new Washington State Convention Center Summit Building—billed as the first high-rise convention center in North America—is on track to complete most of its construction later this year.  

boombox1
boombox2
native1

More In Category


Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021