Removable flood prevention system installed in one of New York City's largest office buildings

Removable flood prevention system installed in one of New York City's largest office buildings

55 Water Street is a virtual city unto itself, with enough excess power to support tenants for multiple days 


By Plaza Construction | March 31, 2014
Directly following Hurricane Sandy in October 2012, Plaza Construction was asked to start working on the development of a flood prevention solution for 55 Water Street, one of New York City’s largest office structures with 54 stories and 3.8 million square feet located in the financial district.  Hurricane Sandy was the second-costliest storm in U.S. history, with damages to New York City estimated at $50 billion due to storm surges flooding streets, tunnels and subway lines and cutting power in and around the city.
 
Plaza Construction, with a team of experts consisting of EKO Flood USA, architect HLW International, and engineer Thornton Tomasetti, along with New Water Street Corporation, the owner/operator of 55 Water Street managed the planning, design and permitting stages to produce the first permitted flood protection system for 55 Water Street. 
 
The new flood barrier protection system installed at 55 Water Street is designed to protect against an eight-foot flood line, higher than the 7-1/2 foot flood line recommended by FEMA to protect against storm surges for the next hundred years. The building was designed by renowned architect Emory Roth and the flood barrier protection system had to fit with the aesthetics of the building. Basically, it had to be invisible to the occupants and visitors of the building.
 
“Plaza was contracted by New Water Street Corporation to help them develop a flood protection system to guard against future storm surges that continue to be a major threat to the infrastructure of New York City and its neighboring communities,” said Richard Wood, CEO, Plaza Construction.  “Together with our partners, we created a simple, fast and easy solution in a modular set up, take down and store removable barrier flood protection system that is tested to withstand an 8-foot flood line.”
 
“The new flood protection system at 55 Water Street is designed to protect the entire building from flooding,” said George Acero, Executive Vice President, New Water Street Corporation. “For efficient preparedness, the building management plans to conduct drills on erecting and breaking down the system on an annual basis.”
 
The flood barrier system at 55 Water Street is based on a removable post and panel flood protection system that easily adapts to the requirements of a particular building site. The system at 55 Water Street is stored in the sub-level of the building and will require 30 men and eight hours to assemble into place, and completely protects the entire building against an 8-foot water line, preventing water from entering the building and seeping into the lower levels.
 
“The advanced design of the EKO system is new to the tri-state region, as we were presenting a unique concept for storm protection,” said Yu-chi Yang, the Project Architect at HLW International. “The final design resulted in a very comprehensive set of guidelines for reviewing similar proposals in the future.”
 
According to the Aine Brazil, Vice Chairman at Thornton Tomasetti, “The integration of the flood barrier system with the existing foundation wall was one key to the economic and practical feasibility, minimizing new foundations in the sidewalk, and providing the necessary continuity of the flood proofed bathtub as an extension of the existing 60 foot deep basement.”
 
Located in downtown Manhattan, 55 Water Street is a virtual city unto itself that provides a fail-safe operating environment. Powerful systems support massive capacities instilling confidence that any crisis can be readily addressed. An extraordinarily advanced technological infrastructure includes multiple redundancies in every major operating system from electric, HVAC, and telecom to life safety and security. Tenants can also avail themselves of sufficient excess power to operate without interruption for multiple days should an emergency situation arise. 
 
“Now with the installation of a removable, flood barrier protection system, 55 Water Street offers added protection in terms of guarding the building against flooding,” adds Mr. Acero.

Related Stories

Products and Materials | Feb 14, 2022

How building owners and developers can get ahead of the next supply chain disaster

Global supply chain interruptions that started at the very beginning of the pandemic are still with us and compounding every step of the way. Below are a few proven tips on how to avert some of the costly fallout should we be faced with similar commercial disasters at any time in the future.

Healthcare Facilities | Feb 10, 2022

Respite for the weary healthcare worker

The pandemic has shined a light on the severe occupational stress facing healthcare workers. Creating restorative hospital environments can ease their feelings of anxiety and burnout while improving their ability to care for patients.

Sponsored | BD+C University Course | Jan 30, 2022

Optimized steel deck design

This course provides an overview of structural steel deck design and the ways to improve building performance and to reduce total-project costs.

Laboratories | Jan 28, 2022

3 must-know strategies for developers in today’s life sciences industry

While the life sciences industry had been steadily growing, this growth exploded when the pandemic arrived—and there is no indication that this lightning-fast pace will slow down any time soon.

M/E/P Systems | Jan 27, 2022

Top 5 building HVAC system problems and how to fix them

When your HVAC system was new, it was designed to keep the indoor environment comfortable, functional, and safe. Over time, that system can drift out of alignment, leading to wasted resources, excessive energy consumption, and reduced occupant comfort.

Market Data | Jan 26, 2022

2022 construction forecast: Healthcare, retail, industrial sectors to lead ‘healthy rebound’ for nonresidential construction

A panel of construction industry economists forecasts 5.4 percent growth for the nonresidential building sector in 2022, and a 6.1 percent bump in 2023.

Sponsored | Steel Buildings | Jan 25, 2022

Multifamily + Hospitality: Benefits of building in long-span composite floor systems

Long-span composite floor systems provide unique advantages in the construction of multi-family and hospitality facilities. This introductory course explains what composite deck is, how it works, what typical composite deck profiles look like and provides guidelines for using composite floor systems. This is a nano unit course.

Sponsored | Reconstruction & Renovation | Jan 25, 2022

Concrete buildings: Effective solutions for restorations and major repairs

Architectural concrete as we know it today was invented in the 19th century. It reached new heights in the U.S. after World War II when mid-century modernism was in vogue, following in the footsteps of a European aesthetic that expressed structure and permanent surfaces through this exposed material. Concrete was treated as a monolithic miracle, waterproof and structurally and visually versatile.

Urban Planning | Jan 25, 2022

Retooling innovation districts for medium-sized cities

This type of development isn’t just about innovation or lab space; and it’s not just universities or research institutions that are driving this change.

boombox1
boombox2
native1

More In Category


Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021