flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

A new BSL-3 public-safety lab debuts in Vermont

A new BSL-3 public-safety lab debuts in Vermont

The project’s Building team is tested by this facility’s complex mechanical system and air exchange requirements. 


By John Caulfield, Senior Editor | November 17, 2014
Vermonts state-of-the-art public safety facility includes unique biosafety labs
Vermonts state-of-the-art public safety facility includes unique biosafety labs that rely on complicated mechanical systems to

The Vermont Department of Health and the University of Vermont in late October held ribbon-cutting ceremonies for a 60,000-sf public health laboratory that is nearly twice the size of the 62-year-old lab it replaces. The laboratory will be used to perform a wide range of analyses to detect biological, toxicological, chemical, and radiological threats to the health of the population, from testing for rabies, West Nile, pertussis and salmonella to water and food contaminants.

The new $31 million facility, located at the Colchester Business and Technology Park, took 18 months from its notice to proceed to its completion. It is distinguished by highly specialized Biosafety Level 3 and Animal Biosafety Level 3 (BSL-3 and ABSL-3) laboratories, as well as high-performance building enclosure, mechanical, electrical, plumbing and fire suppression systems to conduct specialized laboratory work.

That mechanical system accounted for about 40% of the project’s total cost, and posed the biggest installation challenge for Vermont-based PC Construction, the contractor on this project, according to Matt Cooke, PC’s senior project manager. “The building’s ‘penthouse’ is all mechanical, and the facility is jammed-packed with air recovery and exchange equipment.  

He says that “to make everything fit,” PC and the Building Team did extensive BIM modeling That team consisted of HDR (architectural design), Scott & Partners (exterior envelope), Krebs & Lansing (civil engineering), Zero by Design (energy consultation), as well as the State of Vermont Department of Building and General Services and the university (owners).

 


Westphalen Photography

 

PC Construction has built a number “clean rooms” in the past, but nothing as elaborate as this facility, which includes one of the few BSL3 labs in the country, says Cooke. He notes that some of the lab space requires zero leakage, so everything—including the electrical boxes and windows—needed to be sealed. Cooke adds that what also makes the facility unique are its “systems and automated controls” for the anterooms and air exchange machinery.

The building sits on a foundation supported by 180 H-piles that are driven to depths of between 70 and 90 feet. The original plans called for piles that would only need to be 60 to 65 feet deep. “But once we got out there and started drilling,” Cooke says PC found that the geological survey hadn’t sufficiently taken into account the location of underground rocks, which dictated far-deeper piles.

The facility design called for its six flue-gas stacks to be 75 feet above ground, which required FAA approval and a non-reflective coating due to their height and proximity to Burlington International Airport. 

 


Westphalen Photography

 


PC Construction

 


PC Construction

 


PC Construction

Related Stories

Architects | Apr 10, 2017

New Bjarke Ingels documentary gives a peek behind the curtain

The movie takes a slightly darker tone than previous projects chronicling the starchitect’s rise to prominence.

Architects | Apr 4, 2017

Architect Howard Elkus dies at 78

Cofounder of Elkus Manfredi Architects, his career spanned five decades, and included a spectrum of major design projects. 

Building Team | Apr 4, 2017

Dispelling five myths about post-occupancy evaluations

Many assume that post-occupancy (POE) is a clearly-defined term and concept, but the meaning of POE in practice remains wildly inconsistent.

Structural Materials | Apr 3, 2017

Best of structural steel construction: 4WTC, Fulton Center, Pterodactyl win AISC IDEAS2 Awards

The annual awards program, sponsored by the American Institute of Steel Construction, honors the best in structural steel design and construction.

Green | Mar 29, 2017

Copenhagen Zoo and BIG unveil yin yang-shaped panda habitat

The new habitat will sit between two existing buildings, including the Elephant House designed by Norman Foster.

Architects | Mar 28, 2017

A restroom for everyone

Restroom access affects everyone: people with medical needs or disabilities, caretakers, transgender people, parents with children of the opposite gender, and really anyone with issues or needs around privacy.

High-rise Construction | Mar 27, 2017

Density and tall buildings

CRTKL’s Maren Striker examines Europe’s desire to build upward.

Architects | Mar 9, 2017

Watch Frank Lloyd Wright and Buckminster Fuller discuss architecture in animated video shorts

Given more time, Wright wanted to rebuild the country and change the nation.

Architects | Mar 6, 2017

Demolished Frank Lloyd Wright buildings get new life with photorealistic renderings

Architect David Romero recreated the Larkin Administration Building and the Rose Pauson House with detailed, fully colored renderings.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021