Massive mixed-use residential village on USC’s Los Angeles campus on schedule to open this fall

University Buildings

Massive mixed-use residential village on USC’s Los Angeles campus on schedule to open this fall

Prefabrication of the six buildings’ walls reduced construction time by a year. 


By John Caulfield, Senior Editor | March 8, 2017

USC Village, a six-building, 1.25-million-sf expansion of the University of Southern California's University Park campus, will be ready for occpancy this fall. The project took 12 years from conception to completion. Image: USC

This month, work crews began moving furniture, fixtures and equipment into USC Village, the biggest development project in the history of South Los Angeles, which is on schedule to be ready for the fall semester at the University of Southern California’s University Park campus.

The $700 million, 15-acre USC Village, which has been in the works since 2005, will consist of six buildings with a total of 1.25 million sf of space and 2,700 student beds. There will be eight residential colleges within USC Village, four of which had been endowed at presstime. 

To view a flyover of the Village’s construction site, click here.

When USC Village was conceived, it was one of the first mixed-use residential college projects in the nation, and when completed it will include 100,000 sf of retail space for 30 tenants such as Bank of America, Starbucks, Target, and Trader Joe’s (which will be welcomed in South L.A. a food desert when it comes to supermarkets).

The Village will also have food and beverage outlets, and a 30,000-sf fitness center. The Village will provide 1,200 covered bike-parking slots, and another 500 slots for day-to-day bike parking by patrons of the gym or retail stores.

The exterior design of USC Village is best described as “collegiate gothic,” and reflects the mandate by USC’s president C.L. Max Nikias that the look of the Village be connected to the rest of the campus. “We could introduce any design feature, as long as it was gothic,” says Daniel Benjamin, AIA, LEED AP BD+C, Principal and Design Leader for Harley Ellis Devereaux, USC Village’s architect.

That meant a lot of detailing at the ground plane and roof level, but more traditional brick façade in the middle.

Benjamin notes that there weren’t enough masons in southern California to handle of project of this magnitude. So instead of importing workers from other parts of the state, the Building Team—which includes Hathaway Dinwiddie as the GC—decided to precast the concrete facades off site, typically delivered in 12- by 20-ft modules. Brick trimmed with sandblasted warm-colored concrete surrounds gives the buildings a three-dimensional sense of detail.

Prefabrication also cut the construction process, which began in June 2014, by nearly a year. These buildings are designed to last 80-100 years.

During the approval process, three major changes were made to USC Village’s plan, recalls Willy Marsh, USC’s director of construction. A large parking garage with a field on its roof became underground parking. High-rise residential towers became low-rise buildings. And a much larger retail center was de-emphasized. “The decision was made that retail wasn’t going to drive this project,” says Marsh.

 

 

The buildings' facade consists of precast concrete and brickface that mimics older buildings on campus. Image: USC

USC Village comprises about 20% of the University Park campus, and Nikias, says Benjamin, wanted the connections to be seamless. So the Village’s pathways and streets flow seamlessly into the larger campus’s circulation routes. More than 200 trees will be planted within and around the Village.

This campus is an integral part of the surrounding community. As part of this project, USC is providing $40 million in community benefits, including a $20 million contribution to an affordable housing fund that is managed by the city.

The number of student beds could increase to 5,000 if USC decides to redevelop a 12-acre lot adjacent to USC Village. Marsh says that project could be a decade away.

Related Stories

University Buildings | Sep 21, 2015

Vietnamese university to turn campus into ‘terraced forest’

Pockets of plantings will be dispersed throughout the staggered floors of the building, framing the expansive courtyard at its center. 

University Buildings | Sep 21, 2015

6 lessons in campus planning

For campus planning, focus typically falls on repairing the bricks and mortar without consideration of program priorities. Gensler's Pamela Delphenich offers helpful tips and advice.

Mixed-Use | Aug 26, 2015

Innovation districts + tech clusters: How the ‘open innovation’ era is revitalizing urban cores

In the race for highly coveted tech companies and startups, cities, institutions, and developers are teaming to form innovation hot pockets.

University Buildings | Aug 13, 2015

Best of Education Design: 9 projects named AIA Education Facility Design Award winners

Georgia Tech's Clough Commons, Boston's Berklee Tower, and seven other facilities were honored for aiding learning and demonstrating excellent architectural design.

Giants 400 | Aug 7, 2015

UNIVERSITY SECTOR GIANTS: Collaboration, creativity, technology—hallmarks of today’s campus facilities

At a time when competition for the cream of the student/faculty crop is intensifying, colleges and universities must recognize that students and parents are coming to expect an education environment that foments collaboration, according to BD+C's 2015 Giants 300 report.

Contractors | Jul 29, 2015

Consensus Construction Forecast: Double-digit growth expected for commercial sector in 2015, 2016

Despite the adverse weather conditions that curtailed design and construction activity in the first quarter of the year, the overall construction market has performed extremely well to date, according to AIA's latest Consensus Construction Forecast.

University Buildings | Jul 28, 2015

OMA designs terraced sports center for UK's Brighton College

Designs for what will be the biggest construction project in the school’s 170-year history feature a rectangular building at the edge of the school’s playing field. A running track is planned for the building’s roof, while sports facilities will be kept underneath.

University Buildings | Jul 21, 2015

Maker spaces: Designing places to test, break, and rebuild

Gensler's Kenneth Fisher and Keller Roughton highlight recent maker space projects at MIT and the University of Nebraska that provide just the right mix of equipment, tools, spaces, and disciplines to spark innovation. 

University Buildings | Jul 2, 2015

Design for new pavilion in Toronto includes a ‘peel-away’ façade

An architect's proposal for a renovation of the main office building at the Ontario College of Art and Design features a façade that fans out from the edges of the building, like it’s opening up to visitors. 

University Buildings | Jun 29, 2015

Ensuring today’s medical education facilities fit tomorrow’s healthcare

Through thought-leading design, medical schools have the unique opportunity to meet the needs of today’s medical students and more fully prepare them for their future healthcare careers. Perkins+Will’s Heidi Costello offers five key design factors to improve and influence medical education.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021