Manhattan’s Irish Hunger Memorial undergoes $5.3 million renovation

Reconstruction & Renovation

Manhattan’s Irish Hunger Memorial undergoes $5.3 million renovation

The team comprised Battery Park City Authority, CTA Architects, The LiRo Group, and Nicholson & Galloway.


By David Malone, Associate Editor | March 1, 2018

Photo by Edward Menashy

Designed by sculptor and public artist Brian Tolle, the Irish Hunger Memorial is devoted to honor the Great Irish Hunger and Migration of 1845 to 1852. Visitors to the site are taken on a winding path through a rural Irish landscape planted with native Irish plants and stones imported from each of Ireland’s 32 counties. The paths culminate 25 feet above street level with views of the Statue of Liberty and Ellis Island. An Irish Famine-era stone cottage that was disassembled and brought over from Ireland was donated to the Memorial by Tolle’s extended family.

The cottage, pathways, and plant-filled meadows are cantilevered over a layered base of glass and polished fossil-bed limestone from County Kilkenny, Ireland. Frosted glass panels that wrap around the exterior of the Memorial are covered with text that relates to both the Famine and reports of contemporary hunger.

But since it opened in 2002, the memorial has dealt with water infiltration issues and subsequent water damage. Not longer after the Memorial first opened, cracking and leaks from the cantilevered slab where the landscaping and cottage are located were noticed. The leaks were going into the electrical space underneath the Memorial where the glass display cases and lights were installed. The leaks led to efflorescence staining o the glass display panels and discoloration of the partially cantilevered slab.

 

Aerial view of the Irish Hunger MemorialPhoto by Edward Menashy.

 

In 2016, a team comprising Battery Park City Authority, CTA Architects, The LiRo Group, and Nicholson & Galloway began work to restore and weatherproof the Memorial. “Our team recommended carefully removing the landscaping surrounding field-stone masonry walls and portions of the cottage, removing the previously applied and ineffective waterproofing system, performing limited slab repairs and patching, reconfiguration of and reinforcement of the concealed core walls and substrates and then installing a waterproofing membrane, and then assembling the elements of the monument back together,” says CTA Associate and Project Manager for the Memorial, Frank Scanlon, AIA, in a release.

2,000 sf of a reinforced, cold-applied, liquid Kemper 2K PUR system was installed over all exposed core walls and substrates as the main waterproofing measure. The Kemper waterproofing membrane was extended and wrapped around the edge of the slab for additional protection. “The artist, Brian Tolle, expressed some concern, as this made the membrane on the edge of the slab was visible. So we found a mineral surfacing system approved by Kemper that matched the finish of the concrete slab and we incorporated it into the membrane. It completely hides the waterproofing, maintaining visual consistency with the original slab,” says Pericle Gheorghias, CTA’s Senior Technical Designer on the project, in a release.

 

The cantilevered slab of the Irish Hunger MemorialPhoto by Edward Menashy.

 

At the top of the monument, a custom masonry anchoring system for the fieldstone-and-rubble wall was installed to keep the irregularly shaped stones in place. The anchoring system was installed over a sturdy concrete masonry unit core faced with fieldstone and mortar.

Additionally, SiteWorks conducted an existing conditions survey of the soil taken at points every three feet. The information was then used in providing a base for the soil profiles and irrigation layout. The new irrigation system addresses the site’s slope and the use of fast-draining soils. Rotor spray heads irrigate the upper and middle furrow and dripperline tubing irrigates the slope-edge plantings.

The recently completed renovation project cost a total of $5.3 million.

 

Photo by Edward Menashy.

Related Stories

| May 11, 2012

Chapter 10 Action Plan: 18 Recommendations for Advancing Sustainability in Reconstructed Buildings

We offer the following recommendations in the hope that they will help step up the pace of high-performance building reconstruction in the U.S. and Canada. We consulted many experts for advice, but these recommendations are solely the responsibility of the editors of Building Design+Construction. We welcome your comments. Please send them to Robert Cassidy, Editorial Director: rcassidy@sgcmail.com.

| May 11, 2012

Chapter 9 The Key to Commissioning That Works? It Never Stops

Why commissioning for existing and renovated buildings needs to be continuous to be effective.

| May 11, 2012

Chapter 8 High-Performance Reconstruction and Historic Preservation: Conflict and Opportunity

What historic preservationists and energy-performance advocates can learn from each other.

| May 10, 2012

Chapter 7 When Modern Becomes Historic: Preserving the Modernist Building Envelope

This AIA CES Discovery course explores the special reconstruction questions posed by Modern-era buildings.

| May 10, 2012

Chapter 6 Energy Codes + Reconstructed Buildings: 2012 and Beyond

Our experts analyze the next generation of energy and green building codes and how they impact reconstruction.

| May 10, 2012

Chapter 5 LEED-EB and Green Globes CIEB: Rating Sustainable Reconstruction

Certification for existing buildings under these two rating programs has overtaken that for new construction.

| May 10, 2012

Chapter 4 Business Case for High-Performance Reconstructed Buildings

Five reconstruction projects in one city make a bottom-line case for reconstruction across the country.

| May 10, 2012

Chapter 3 How Building Technologies Contribute to Reconstruction Advances

Building Teams are employing a wide variety of components and systems in their reconstruction projects.

| May 9, 2012

Chapter 1 Reconstruction: ‘The 99% Solution’ for Energy Savings in Buildings

As a share of total construction activity reconstruction has been on the rise in the U.S. and Canada in the last few years, which creates a golden opportunity for extensive energy savings.

boombox1
boombox2
native1

More In Category


Adaptive Reuse

Empty mall to be converted to UCLA Research Park

UCLA recently acquired a former mall that it will convert into the UCLA Research Park that will house the California Institute for Immunology and Immunotherapy at UCLA and the UCLA Center for Quantum Science and Engineering, as well as programs across other disciplines. The 700,000-sf property, formerly the Westside Pavilion shopping mall, is two miles from the university’s main Westwood campus. Google, which previously leased part of the property, helped enable and support UCLA’s acquisition.


Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021