L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

Codes and Standards | Dec 2, 2019

New GBCI certification recognizes expertise in sustainability

Provides third-party verification of competency to ‘making the world more economically, socially, and environmentally sustainable.’

Codes and Standards | Dec 2, 2019

New tool allows users to learn how to reduce embodied carbon

Calculator delivers first digitized EPDs.

Codes and Standards | Dec 2, 2019

Trade group challenges St. Petersburg, Fla., ordinance on construction contract mandates

Legality of requirement to hire apprentices, disadvantaged workers at issue.

Building Owners | Dec 2, 2019

What building owners and AEC teams need to know about New York’s Climate Mobilization Act

On April 18, 2019, the New York City Council passed the Climate Mobilization Act, a suite of laws aimed to meet the city’s commitment to achieving carbon neutrality by 2050.

Codes and Standards | Nov 26, 2019

Updated ASHRAE standards focused on ventilation design, air quality in residential applications

Standard 62.1 and 62.2 updates provide new tables of ventilation rates per unit area.

Codes and Standards | Nov 25, 2019

Real estate professionals say coworking is not a flash in the pan

More than 60% say coworking space is in their portfolios.

Codes and Standards | Nov 22, 2019

Utility’s proposal threatens California’s rooftop solar mandate

Would allow customers to use solar farms instead of installing their own PVs.

Codes and Standards | Nov 21, 2019

Number of LEED commercial building projects surpasses 100,000

More than 2.6 million sf of space being certified each day.

Codes and Standards | Nov 19, 2019

Most U.S. voters support licensing standards for architects

NCARB survey shows strong support for architecture as a licensed profession.

Codes and Standards | Nov 18, 2019

Cambridge, Mass., teams up with utility on energy retrofit program

Buildings large than 25,000 sf targeted in initiative to further carbon neutrality goal.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021