L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

| Dec 4, 2013

Five U.S. cities leading on climate change initiatives

Houston, Salt Lake City, Miami, New York, and Los Angeles are five cities that are leading the way on preparing for climate change and extreme weather, according to a Center for American Progress report.

| Dec 4, 2013

Philadelphia City Council mulling bill requiring ID cards for construction workers

The Philadelphia City Council has held a series of hearings on a bill aimed at boosting the city's safety regulations in the wake of a deadly building collapse earlier this year.

| Dec 4, 2013

Changes completed on 2015 IECC provisions

The 2015 International Energy Conservation Code (IECC)—the code that serves as the model for states’ codes—has undergone final changes.

| Dec 4, 2013

Design-build makes gains along with more authorizing legislation

In 2009, more legislation authorizing design-build project delivery passed than in any year in Design Build Institute of America’s history.

| Dec 4, 2013

Rotterdam resiliency policies include floating neighborhood

The low-lying city of Rotterdam in the Netherlands is a world leader in storm resiliency with policies that impact businesses, private homes, and public infrastructure.

| Dec 4, 2013

Meet the 'world's greenest building': One Angel Square

The 500,000 sf, 14-story One Angel Square in Manchester, England, is being promoted as "the most environmentally-friendly building in the world."

| Dec 3, 2013

Architects urge government to reform design-build contracting process

Current federal contracting laws are discouraging talented architects from competing for federal contracts, depriving government and, by inference, taxpayers of the best design expertise available, according to AIA testimony presented today on Capitol Hill.

| Nov 27, 2013

ASHRAE data center standard open for public review

Standard 90.4P, Energy Standard for Data Centers and Telecommunications Buildings, is being developed in response to requests to recognize the energy performance profiles unique to data centers. 

| Nov 27, 2013

Ohio legislators move to ban use of LEED on public construction

Two Ohio state senators have introduced legislation that seeks to ban the use of LEED in public construction.

| Nov 27, 2013

ASTM issues revised standard on phase I environmental site assessments

ASTM has issued revised standard ASTM E1527-13 that governs phase I environmental site assessments.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021