L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

Codes and Standards | May 7, 2015

New OSHA rule aimed at protecting construction workers in confined spaces

The agency says the rule will protect about 800 workers a year from serious injury.

Codes and Standards | May 1, 2015

Colorado House kills construction defects bill

The legislation would have made it harder for condo owners to sue builders.

Codes and Standards | May 1, 2015

New energy efficiency program, Tenant Star, gets OK from Congress

The voluntary program for commercial and government buildings is modeled after Energy Star.

Smart Buildings | May 1, 2015

FEMA to require states to evaluate risks posed by climate change

The aim is for states to do a better job planning for natural disasters they are likely to face in a warming world.

Codes and Standards | May 1, 2015

Department of Energy asks for feedback on cost-effectiveness of building energy codes

DOE’s RFI wants input on how to improve methodology on cost assessment.

Codes and Standards | Apr 22, 2015

New York State renews design-build authority

Five state agencies are allowed to use design-build on certain projects.

Codes and Standards | Apr 22, 2015

OSHA’s estimated cost of silica rule said to underestimate impact by $4.5 billion annually

The coalition says that OSHA’s flawed cost estimates point to flaws in the rule, and has urged the federal agency to reconsider its approach. 

Codes and Standards | Apr 22, 2015

GBCI renamed Green Business Certification Inc.

The name change reflects the organization’s expanded certification and credentialing services.

Multifamily Housing | Apr 16, 2015

Seattle’s size restriction on micro apartments blamed for rise in rents

Seattle’s city planner recently said that the council’s new rules have made small apartments more expensive to build and charged the board with “overreaching” and not giving micro-housing “a fair shake.”

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021