L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

Codes and Standards | Jun 18, 2015

Two myths regarding NFPA 101 Life Safety Code debunked

NFPA life safety engineer Ron Coté settles the debate over second egress doors and exit signs.

Codes and Standards | Jun 18, 2015

How to prevent corrosion in sprinkler system piping

The technical committees responsible for NFPA 13, Installation of Sprinkler Systems, have been looking at ways to eliminate or reduce corrosion in sprinkler systems for several revision cycles.

Codes and Standards | Jun 11, 2015

Steel Framing Alliance updates ‘Thermal Design and Code Compliance for Cold-Formed Steel Walls’ design guide

Includes results of new tests and addresses IECC and ASHRAE compliance paths.

Codes and Standards | Jun 11, 2015

Helena, Mont., may charge commercial developers a fee to fund public art

The fee would apply to new construction or alteration of nonresidential buildings of at least 20,000 sf.

Codes and Standards | Jun 11, 2015

DBIA releases new document on choosing a project delivery method

Provides owners and others with factors to consider when choosing the best method of delivery for their project.

High-rise Construction | Jun 5, 2015

Japanese policymakers discuss mandate for toilets in elevators

This quirky-sounding building code is a safety measure for the earthquake-prone nation.

Codes and Standards | Jun 4, 2015

OSHA publishes guide to restroom access for transgender workers

The guide advises employers to allow employees to use restrooms that correspond to their gender identity.

Codes and Standards | Jun 4, 2015

Guide helps Building Teams maximize team integration

The guide includes forms to support a two- to four-hour workshop to help an owner select the most appropriate delivery strategy. 

Codes and Standards | Jun 4, 2015

NIBS, RICS to explore P3 as tool to achieve high-performance buildings

The idea of applying the P3 concept more to buildings, and especially building performance, is a potentially promising new avenue in the U.S., according to the trade groups.

University Buildings | May 30, 2015

Texas senate approves $3 billion in bonds for university construction

For the first time in nearly a decade, Texas universities could soon have some state money for construction.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021