L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

Codes and Standards | May 15, 2018

Blast testing of loaded mass timber structures yields positive results

Four tests covered a spectrum of blast loads.

Codes and Standards | May 14, 2018

Maryland makes general contractors liable for failure of subs to pay employees

GCs could have to pay for up to three times the wages owed.

Codes and Standards | May 10, 2018

Data collection, machine learning boost building efficiency

Sensors, software algorithms squeeze out waste.

Codes and Standards | May 9, 2018

OSHA and state safety agencies write more than 100 silica citations in 6 months

Actions tending to come with investigation of other site conditions.

Codes and Standards | May 8, 2018

Powerhouse coalition builds energy positive buildings

The goal: build buildings that provide more power than they cost to build, run, and demolish.

Codes and Standards | May 7, 2018

Plan advances in Los Angeles for Climate Emergency Mobilization Department

Would oversee efforts to reduce greenhouse gas emissions across the city.

Codes and Standards | May 3, 2018

Data collection, machine learning boost building efficiency

Sensors, software algorithms squeeze out waste.

Codes and Standards | May 1, 2018

ASHRAE publishes new energy simulation-aided design standard

Requires building energy modeling during schematic design.

Codes and Standards | Apr 30, 2018

CALGreen projects pre-approved for streamlined LEED v4 requirements

Reduces need to run additional energy models.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021