The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.
The new building was Singaporeās first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.
Ā
Photo: Patrick Bingham-Hall.
Ā
The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.
Ā
Photo: Patrick Bingham-Hall.
Ā
āThe Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,ā says Singaporeās Building and Construction Authority CEO John Keung in a release.
Ā
Photo: Patrick Bingham-Hall.
Related Stories
| Aug 11, 2010
HDR, Perkins+Will top BD+C's ranking of the nation's 100 largest healthcare design firms
A ranking of the Top 100 Healthcare Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
Arup, SOM top BD+C's ranking of the country's largest mixed-use design firms
A ranking of the Top 75 Mixed-Use Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
10% of world's skyscraper construction on hold
Emporis, the largest provider of global building data worldwide, reported that 8.7% of all skyscrapers listed as "under construction" in its database had been put on hold. Most of these projects have been halted in the second half of 2008. According to Emporis statistics, the United States had been hit the worst: at the beginning of 2008, "Met 3" in Miami was the only U.S. skyscraper listed as being "on hold". In the second half of the year, 19 projects followed suit.
| Aug 11, 2010
Structure Tone, Turner among the nation's busiest reconstruction contractors, according to BD+C's Giants 300 report
A ranking of the Top 75 Reconstruction Contractors based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
Best AEC Firms of 2011/12
Later this year, we will launch Best AEC Firms 2012. Weāre looking for firms that create truly positive workplaces for their AEC professionals and support staff. Keep an eye on this page for entry information. +