A grim Market Outlook foresees more shortages that impede construction

Contractors

A grim Market Outlook foresees more shortages that impede construction

Consigli’s new report, though, does offer glimmers of relief on the supply-chain front, and strategies for risk management.


By John Caulfield, Senior Editor | October 29, 2021
Consigli's latest market outlook expects labor shortages to continue through next year. Image: Pixabay
Labor shortages continue to impact construction projects, and could get worse next year, according to Consigli's latest Market Outlook. Image: Pixabay

The good news: the cargo and transportation snags that have encumbered building material availability this year showed signs of finally easing in September.

The bad news: the lack of material supply and increasing demand for labor are keeping prices high, to the point where manufacturers aren’t willing to hold price quotes for more than a week, if at all.

That, in a nutshell, is the state of the construction market, which the general contractor Consigli lays out in its Market Outlook for October 2021. The Outlook, written by the firm’s Director of Purchasing Peter Capone and Vice President of Preconstruction Jared Lachapelle, sends up red alerts about the availability of six product categories—steel joist, steel deck, MEP equipment, roofing insulation, lab casework, and mineral/rock wool—whose lead times for fabrication after release, as of Sept. 1, ranged from 20 to 40 weeks, with steel joists having the longest wait time.

The Outlook reports a 12 percent average price escalation for the 15 building materials tracked, and anticipates another 3 percent bump through the final quarter of this year. Roofing insulation, roofing membranes, gypsum wallboard, light-gauge metal framing, and glass exceed the overall averages.

As a result of large manufacturers not willing to take risks on escalating prices. “subcontractors are being changed market increases at the time of delivery,” states the report.

 

The lead times for several building materials exceeds 20 weeks. Image: Consigli
Consigli identifies several building materials for which there have been “significant” lead time delays and price hikes. Image: Consigli
 

MANAGING RISK TAKES DISCIPLINE

Consigli’s strategies for risk management include:

•lock in prices with subs that are willing to share risk

•buy in bulk quantities whenever possible

•consider alternative supply sources

•implement stringent quality assurance and control measures

•focus on weekly materials delivery verification

•pre-purchase and warehouse materials

•identify peak manpower needs

•utilize prefabrication that takes labor off site

•partner with trades through design-assist

Consigli thinks labor shortages could get worse in the second half of next year. The severity will depend, in part, on vaccination mandates at a time when a sizable number of construction workers still refuse to be vaccinated. But even a fully vaccinated workforce might struggle to keep pace with construction demand that the pending $1 trillion infrastructure bill, if passed, would further pressure.

The Outlook notes that some manufacturers are focusing their production capacities on commonly used materials like drywall and MEP equipment, which is limiting—and sometimes halting—the production of specialty products. And AEC firms need to be vigilant about maintaining compatibility and quality when manufacturers source products from alternate vendors.

Consigli sees some light at the end of this supply tunnel. Its Outlook notes that steel prices are starting to level off as production increases. But citing the National Roofing Contractors Association, Consigli also cautions that shortages in roofing materials and insulation (whose lead time right now is 24 weeks) will continue through next year because of raw materials supply issues.

Related Stories

High-rise Construction | Apr 16, 2015

Construction begins on Seattle's Tibet-inspired Potala Tower

Construction on the 41-story Potala Tower in Seattle finally kicked off following a ground-breaking ceremony seven months ago.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 10, 2015

Prefab saves the day for Denver hospital

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 10, 2015

Virtual collaboration helps complete a hospital in 24 months

PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.

Building Team Awards | Apr 10, 2015

New arts venue reinvigorates Virginia Tech's campus

The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.

Building Team Awards | Apr 9, 2015

Multifaced fitness center becomes campus landmark

A sloped running track and open-concept design put this Building Team to the test. 

Building Team Awards | Apr 9, 2015

Nation's first LEED-certified bus depot

A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.

Building Team Awards | Apr 9, 2015

Setting the bar for port-of-entry design

Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.

Building Team Awards | Apr 9, 2015

Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C

Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.

boombox1
boombox2
native1

More In Category


Resiliency

Austin area evacuation center will double as events venue

A new 45,000 sf FEMA-operated evacuation shelter in the Greater Austin metropolitan area will begin construction this fall. The center will be available to house people in the event of a disaster such as a major hurricane and double as an events venue when not needed for emergency shelter.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021