Google to convert an Alabama coal-burning plant to a data center running on clean energy

Industrial Facilities

Google to convert an Alabama coal-burning plant to a data center running on clean energy

This would be the tech giant’s seventh data center in the U.S.


By John Caulfield, Senior Editor | June 26, 2015
Google to convert an Alabama coal-burning plant to a data center running on clean energy

This October, Tennessee Valley Authority will close its outdated Widows Creek coal plant in Stevenson, Ala., which had been providing energy to the region since the 1960s. Photo: TVA Web Team via Wikimedia Commons

The coal-producing industry has taken its lumps of late, a victim of natural gas fracking and restrictions on air pollution. This October, Tennessee Valley Authority (TVA) will finally close its outdated Widows Creek coal plant in Stevenson, Ala., which had been providing energy to the region since the 1960s, rather than knock heads with the EPA over tighter financial and environmental regulations.

That plant, located on 350 acres about 60 miles northeast of Huntsville, will be retrofitted into a data center that runs on renewable energy. Google has agreed to build this $600 million project, which would be its 14th data center globally, but the first it has committed to in eight years, according to the San Antonio Express-News.

Google’s data centers in Iowa and Oklahoma run on wind power, and the Alabama facility will operate solely on renewable energy, possibly a combination of wind and solar.

The company states on its website that it has recently expanded its data centers in the states of Georgia and Iowa, as well as in Singapore and Belgium. Construction on the Alabama plant is scheduled to begin early next year and to bring between 75 and 100 jobs to Jackson County.

Google’s data centers in Iowa and Oklahoma run on wind power, and the Alabama facility will operate solely on renewable energy, possibly a combination of wind and solar, the company states. The data center will be hooked up to TVA’s electrical transmission lines, and Google will work with the Authority to run renewable energy through the latter’s electrical grid.

Alabama Gov. Robert Bentley called this project “the start of a long-lasting, productive relationship with Google.” He credited the TVA’s chairman Joe Ritch for securing the project. Google will benefit from two state tax-abatement packages that stem from the passage, three years ago, of the Alabama Data Processing Center Incentive Enhancement Act, according to AL.com.

Gary Demasi, Google’s director of Global Infrastructure, said in a prepared statement that Google sees “a lot of potential in redeveloping large industrial sites like former coal plants, and we’re excited to bring a data center to Alabama.” Urs Hölzle, Google’s SVP for technical infrastructure, told the New York Times that the company would be evaluating “plausible projects” over the next 12 months.

The data center is expected to incorporate Google’s latest technology efficiencies, which allow it to get 3.5 times the computing power out of the same amount of energy, compared to five years ago.

Related Stories

| May 29, 2014

7 cost-effective ways to make U.S. infrastructure more resilient

Moving critical elements to higher ground and designing for longer lifespans are just some of the ways cities and governments can make infrastructure more resilient to natural disasters and climate change, writes Richard Cavallaro, President of Skanska USA Civil.

| May 26, 2014

New Jersey data centers will manage loads with pods

The two data center facilities totaling almost 430,000 sf for owner Digital Realty Trust will use the company's TK-Flex planning module, allowing for 24 pods.

| May 22, 2014

BIM-driven prototype turns data centers into a kit of parts

Data center design specialist SPARCH creates a modular scheme for solutions provider Digital Realty.

| May 22, 2014

Facebook, Telus push the limits of energy efficiency with new data centers

Building Teams are employing a range of creative solutions—from evaporative cooling to novel hot/cold-aisle configurations to heat recovery schemes—in an effort to slash energy and water demand.

| May 22, 2014

7 ways it pays to use BIM for data centers

Here’s where AEC firms and owners are getting the most bang for the buck when using BIM/VDC to coordinate data center projects.

| May 22, 2014

Big Data meets data centers – What the coming DCIM boom means to owners and Building Teams

The demand for sophisticated facility monitoring solutions has spurred a new market segment—data center infrastructure management (DCIM)—that is likely to impact the way data center projects are planned, designed, built, and operated. 

| May 20, 2014

Kinetic Architecture: New book explores innovations in active façades

The book, co-authored by Arup's Russell Fortmeyer, illustrates the various ways architects, consultants, and engineers approach energy and comfort by manipulating air, water, and light through the layers of passive and active building envelope systems.

| May 19, 2014

What can architects learn from nature’s 3.8 billion years of experience?

In a new report, HOK and Biomimicry 3.8 partnered to study how lessons from the temperate broadleaf forest biome, which houses many of the world’s largest population centers, can inform the design of the built environment.

| May 13, 2014

19 industry groups team to promote resilient planning and building materials

The industry associations, with more than 700,000 members generating almost $1 trillion in GDP, have issued a joint statement on resilience, pushing design and building solutions for disaster mitigation.

| May 11, 2014

Final call for entries: 2014 Giants 300 survey

BD+C's 2014 Giants 300 survey forms are due Wednesday, May 21. Survey results will be published in our July 2014 issue. The annual Giants 300 Report ranks the top AEC firms in commercial construction, by revenue.

boombox1
boombox2
native1

More In Category

Industrial Facilities

8 ways to cool a factory

Whichever way you look at it—from a workplace wellness point of view or from a competing for talent angle—there are good reasons to explore options for climate control in the factory workplace.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021