Contractors should scrutinize contracts carefully amid Covid-19 crisis

Codes and Standards

Contractors should scrutinize contracts carefully amid Covid-19 crisis

Compliance with time-sensitive notice requirements and careful documentation required.


By Peter Fabris, Contributing Editor | March 23, 2020

Courtesy Pixabay

During the Covid-19 virus crisis, it is important for contractors to protect themselves from possible legal action by adhering to the provisions of current contracts, lawyers advise.

“The virus and its economic impact will almost alter pre-existing plans for owners, developers, general contractors, subcontractors, and everyone else down the chain,” according to Balch & Bingham LLP. “While many are understanding of these circumstances, there are ways to ensure you are protected going forward.” They advise:

· Review on-going contracts and locate their delay, force majeure, change order, termination, suspension and other relevant provisions.

· Comply with time-sensitive notice requirements. This includes supply agreements and insurance policies. When there is uncertainty over whether to invoke a provision in a document, consider putting the other party on notice to protect your rights.

· Scrupulously document developments. “Proving delays, labor shortages, supply interruption, and other project impacts tomorrow will depend on the evidence being created (or not being created) today.” Simple email or daily notes are acceptable to record the impacts from COVID-19.

· Check your insurance coverage. Business interruption insurance typically includes complex provisions and exclusions.

· Anticipate operational problems. “Administrative tasks might be easily completed from home while supply chains may be severely limited by a reduced and quarantined workforce thousands of miles away.” Anticipate likely problems and try to plan for them.

Related Stories

Codes and Standards | Nov 30, 2020

Finalized 2021 Energy Code leaves out future-proofing provision

Appeals process nixed requirement for residential electrification readiness.

Codes and Standards | Nov 23, 2020

GBCI turns over GRESB ownership to global investment firm

Organization assesses sustainability performance of real estate and infrastructure portfolios and assets.

Codes and Standards | Nov 23, 2020

New industrywide clay brick EPD launched

Contributes toward LEED v.4.0 and v.4.1 materials and resources requirements.

Codes and Standards | Nov 18, 2020

Commissioning study finds median energy savings of 3% to 16%

Berkeley Lab examines results of commissioning across building types.

Codes and Standards | Nov 17, 2020

Midtown Manhattan’s empty offices could be converted to affordable housing

Advocates envision idle offices re-zoned to alleviate housing crisis.

Codes and Standards | Nov 16, 2020

New concrete detailing manual includes downloadable CAD files

American Concrete Institute document contains guidance on codes for structural concrete.

Codes and Standards | Nov 12, 2020

California rent control measure defeated

Golden State voters reject Proposition 21.

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021