Contractors should scrutinize contracts carefully amid Covid-19 crisis

Codes and Standards

Contractors should scrutinize contracts carefully amid Covid-19 crisis

Compliance with time-sensitive notice requirements and careful documentation required.


By Peter Fabris, Contributing Editor | March 23, 2020

Courtesy Pixabay

During the Covid-19 virus crisis, it is important for contractors to protect themselves from possible legal action by adhering to the provisions of current contracts, lawyers advise.

“The virus and its economic impact will almost alter pre-existing plans for owners, developers, general contractors, subcontractors, and everyone else down the chain,” according to Balch & Bingham LLP. “While many are understanding of these circumstances, there are ways to ensure you are protected going forward.” They advise:

· Review on-going contracts and locate their delay, force majeure, change order, termination, suspension and other relevant provisions.

· Comply with time-sensitive notice requirements. This includes supply agreements and insurance policies. When there is uncertainty over whether to invoke a provision in a document, consider putting the other party on notice to protect your rights.

· Scrupulously document developments. “Proving delays, labor shortages, supply interruption, and other project impacts tomorrow will depend on the evidence being created (or not being created) today.” Simple email or daily notes are acceptable to record the impacts from COVID-19.

· Check your insurance coverage. Business interruption insurance typically includes complex provisions and exclusions.

· Anticipate operational problems. “Administrative tasks might be easily completed from home while supply chains may be severely limited by a reduced and quarantined workforce thousands of miles away.” Anticipate likely problems and try to plan for them.

Related Stories

Codes and Standards | Dec 16, 2020

Resources available to address Legionella threat

Buildings reopened after extended pandemic closure are at risk.

Codes and Standards | Dec 16, 2020

New Specifications for Concrete Construction reference manual released

Scope expanded to include shotcrete, internal curing, mineral fillers, and recycled concrete aggregates.

Codes and Standards | Dec 15, 2020

Despite COVID-19 population flight, don’t write off big cities yet

Lure of urban life and jobs may draw people back after pandemic subsides.

Codes and Standards | Dec 10, 2020

Test method for vertical fenestration installation procedures updated

FGIA issues first update for document created in 2005.

Codes and Standards | Dec 9, 2020

Newly formed Rainscreen Association aims to be recognized authority on rainscreen assemblies

Will address innovations in material performance and building designs.

Codes and Standards | Dec 9, 2020

Investors want building resiliency plans and risk mitigation practices

Owners should assess risk, insurance coverage, and ability to withstand disasters.

Codes and Standards | Dec 4, 2020

OSHA cites more than 200 employers for COVID-19 violations

Agency releases guidance on lessons learned from pandemic inspections.

Codes and Standards | Dec 1, 2020

Pandemic spurs nearly 16 million people to move from major cities

Most of the movement seems permanent.  

Codes and Standards | Nov 30, 2020

USGBC ready to catalyze LEED Positive future

New programs, updates will spur shift to regenerative strategies.  

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021