Boulder, Colo., puts sustainable deconstruction policy into action

Reconstruction & Renovation

Boulder, Colo., puts sustainable deconstruction policy into action

Three quarters of a closed hospital’s building materials and equipment are being reused for new construction, or resold.


By John Caulfield, Senior Editor | May 26, 2023
Materials from a demolished hospital in Colorado will be reused in new construction.
Materials from a demolished hospital in Boulder, Colo., will find new life in construction projects, as part of that city's mandate to dramatically reduce what goes into its landfills. Images: Courtesy of Ameresco

Ameresco, a Massachusetts-based cleantech integrator and renewable energy owner and operator, has been working with the City of Boulder, Colo., on the company’s first sustainable deconstruction project, a demolition of the municipality’s former Boulder Community Health Hospital, which had been closed since April 2019.

Boulder has set a target to divert 85 percent of the city’s waste away from landfills by 2025. The former hospital’s deconstructed building materials, and specifically its structural steel, will be used to construct a new fire station and other projects within the city. The firehouse, to be located at 30th and Valmont in Boulder, is scheduled to open in mid-2024. During an early deconstruction phase, the hospital’s pumps, motors, doors, and fixtures, as well as other materials, were auctioned rather than dumped into landfills. 

The 250,000-sf hospital’s demolition occurred in two phases, says Rob Sevier, Ameresco’s Senior Account Executive in Denver: the interior demo began in 2019, was slowed because of COVID, and was completed last year. The exterior demo—which includes removing the hospital’s concrete floors, steel, and exteriors—required new permits before it was started last March. Sevier says the deconstruction should be completed sometime this fall.

“This deconstruction project is an important foundational example of innovative sustainability for the communities where we live and work,” said Louis Maltezos, Ameresco’s Executive Vice President, in a prepared statement. Based in Chicago, Maltezos oversees the company’s activities in the central U.S. and in Canada.

The cost of the demolition, and how much of that cost is expected to be recouped by reusing or reselling materials and equipment from the deconstruction, were not available at presstime, according to an Ameresco spokesperson.

Mandate calls for dramatic reuse

Aggregate will fill the hole created by the hospital demo.
Crushed rock and other aggregate will be reused to fill the hole created by the hospital's demolition.
 

In July 2020, Boulder passed a deconstruction ordinance that covers both residential and commercial properties and requires that at least 75 percent by weight of building materials generated from deconstruction must be recycled, reused or go for organics management. Demolition permits now also require a refundable deconstruction deposit of $1 per sf of the structure, with a $1,500 minimum.

Concerning the hospital demo project, Mike White, who works for Ameresco in Boulder, told Aspen Public Radio that “this project is all about reusing, and that’s the key word, reuse versus recycle.”

He said the building’s mortar, brick and concrete are getting crushed into construction grade, compacted, and reused to fill the hole left by the hospital demo. (The site is being redeveloped for affordable housing.) Right now, steel removed from the hospital is being stored onsite, but Sevier says Ameresco and the city will need to find a warehouse once the housing construction gets underway. “It’s also my understanding that Boulder wants to use this steel for other projects,” he says.

The hospital deconstruction contributes to the city’s Circular Boulder program that keeps materials out of landfills and in use as much as possible. “This growing area of work moves beyond recycling and composting to focus on preventing waste and pollution in the first place. It explores innovative ways to curb Boulder’s collective consumption through reuse and repair.”

Along with its waste reduction goals, Boulder is also striving for carbon neutrality by 2035.

Sevier says that reusing the hospital’s steel required having a structural engineer sign off on the materials’ integrity. There was also an extensive permitting process, and safety plans that included asbestos remediation. But that effort was worth it, he says, because “when we can reuse something, we’re also avoiding the impact of generating something new.”

Ameresco isn’t actively looking for other sustainable deconstruction opportunities. The company has had a longstanding business relationship with the City of Boulder, which Sevier points out is more environmentally progressive than most other metros. But the company’s M.O., says its director of marketing and public relations Rhea Hickok, “is to do what makes sense for our customers.” In the future, that is likely to mean “how sustainability fits in,” she says.

Related Stories

Performing Arts Centers | Aug 31, 2016

Sydney Opera House scheduled for $200 million upgrade

Acoustical improvements will be made alongside upgrades in accessibility, efficiency, and flexibility.

Reconstruction & Renovation | Aug 29, 2016

Home maintenance 101: How uninformed homeowners can cause developers big headaches, and what to do about it

By taking a proactive stance, the home-building industry can both educate the public about the importance of home maintenance and raise awareness within the construction community about protecting their professional rights and reputations.

Great Solutions | Aug 23, 2016

Reusable infection control barriers ease hospital renovation

Clark Construction Group pilots the Edge Guard system on the Fair Oaks (Va.) Hospital reconstruction project.

| Aug 19, 2016

RECONSTRUCTION GIANTS: Facelifts give buildings new identities, even as they keep a few wrinkles

Reconstruction is always a balancing act between the client’s pro forma and what the building needs to be vibrant again.

| Aug 19, 2016

Top 70 Reconstruction Engineering Firms

Jacobs, Robins & Morton, and The Boldt Company top Building Design+Construction’s annual ranking of the nation’s largest reconstruction sector engineering and E/A firms, as reported in the 2016 Giants 300 Report.

| Aug 19, 2016

Top 110 Reconstruction Construction Firms

Gilbane Building Co., Turner Construction Co., and The Whiting-Turner Contracting Co. top Building Design+Construction’s annual ranking of the nation’s largest reconstruction sector construction and construction management firms, as reported in the 2016 Giants 300 Report.

| Aug 19, 2016

Top 130 Reconstruction Architecture Firms

The Beck Group, Stantec, and IMC Consruction top Building Design+Construction’s annual ranking of the nation’s largest reconstruction sector architecture and A/E firms, as reported in the 2016 Giants 300 Report.

Reconstruction & Renovation | Aug 16, 2016

Community organization celebrating 25 years of safer, healthier homes

Rebuilding Together Metro Chicago’s work engages 3,500 volunteers every year to work on more than 100 repair projects for local residents in need.

Reconstruction & Renovation | Aug 9, 2016

Renascent architecture: Demolished Frank Lloyd Wright structures get new life

The Frank Lloyd Wright Revival Initiative is set to begin its reconstruction efforts with the Banff Pavilion, which was demolished in 1939.

Performing Arts Centers | Jun 16, 2016

Synagogues in Omaha and New York get new lives after intense reconstruction

The Omaha Conservatory of Music gets a new home in a temple. A fire leads to an ambitious rebuild for a NYC synagogue.

boombox1
boombox2
native1

More In Category




Mass Timber

British Columbia hospital features mass timber community hall

The Cowichan District Hospital Replacement Project in Duncan, British Columbia, features an expansive community hall featuring mass timber construction. The hall, designed to promote social interaction and connection to give patients, families, and staff a warm and welcoming environment, connects a Diagnostic and Treatment (“D&T”) Block and Inpatient Tower.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021