Associated Builders and Contractors reported today that its Construction Backlog Indicator increased to 9.3 months in July, according to an ABC member survey conducted July 20 to Aug. 4. The reading is up by 0.6 months since July 2022.
The South remains the region with the highest level of backlog, despite being the only region with lower backlog on a year-ago basis. Backlog gains in July were concentrated in the commercial and institutional category.
“Nonresidential construction backlog continues to expand, which is precisely what contractors had predicted six months ago," said ABC Chief Economist Anirban Basu. "For many months, contractors have been signaling an expectation that demand for their services would continue to expand despite high and rising interest rates and a spate of regional bank failures.
“That said, there are some surprises in the data,” said Basu. “Backlog declined in both the infrastructure and heavy industry categories, possibly because the current administration is striving to reserve many large-scale projects for unionized firms. ABC members are largely nonunion, and therefore may be locked out of a meaningful proportion of significant opportunities. Diminished competition for such projects would tend to drive up construction service delivery charges, much of which are financed by American taxpayers."
ABC’s Construction Confidence Index reading for profit margins and staffing levels moved higher in July, while the reading for sales fell slightly. All three readings remain above the threshold of 50, indicating expectations of growth over the next six months.
Related Stories
Coronavirus | May 26, 2020
9 tips for mastering virtual public meetings during the COVID-19 pandemic
Mike Aziz, AIA, presents 9 tips for mastering virtual public meetings during the COVID-19 pandemic.
Coronavirus | May 18, 2020
Infection control in office buildings: Preparing for re-occupancy amid the coronavirus
Making workplaces safer will require behavioral resolve nudged by design.
Data Centers | May 8, 2020
Data centers as a service: The next big opportunity for design teams
As data centers compete to process more data with lower latency, the AEC industry is ideally positioned to develop design standards that ensure long-term flexibility.
Coronavirus | Apr 30, 2020
Gilbane shares supply-chain status of products affected by coronavirus
Imported products seem more susceptible to delays
Coronavirus | Apr 14, 2020
COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients
Missouri’s first Alternate Care Facility ready for coronavirus patients
AEC Tech | Apr 13, 2020
A robotic dog becomes part of Swinerton’s construction technology arsenal
Boston Dynamics, the robot’s creator, has about 100 machines in the field currently.
Coronavirus | Apr 8, 2020
COVID-19 alert: Most U.S. roofing contractors hit by coronavirus, says NRCA
NRCA survey shows 52% of roofing contractor said COVID-19 pandemic was having a significant or very significant impact on their businesses.
Coronavirus | Apr 5, 2020
COVID-19: Most multifamily contractors experiencing delays in projects due to coronavirus pandemic
The NMHC Construction Survey is intended to gauge the magnitude of the disruption caused by the COVID-19 outbreak on multifamily construction.
Coronavirus | Apr 4, 2020
COVID-19: Construction completed on first phase of Chicago's McCormick Place into Alternate Care Facility
Walsh Construction, one of the largest contractors in the city of Chicago and in the United States, is leading the temporary conversion of a portion of the McCormick Place Convention Center into an Alternate Care Facility (ACF) for novel coronavirus patients. Construction on the first 500 beds was completed on April 3.