Addressing client concerns about design-assist

Building Team

Addressing client concerns about design-assist

Common concerns about DA include lack of familiarity, obtaining competitive pricing, and design liability.


By Tom Garske, Jennifer Horvath, Ed Keener, Stephen Metz, Jeff Ortman, Randy Sleeper, Kurt Smith, and Monica Wangler | Ohio Construction Transformation Consortium | July 11, 2016

Construction in Miami in July 2016. Photo: Phillip Pessar/Creative Commons.

Design-assist is not without potential drawbacks. Here are some common concerns—and how your Building Team can reassure clients that DA is worth considering.

OWNER CONCERN: Lack of familiarity with design-assist. DA is a relatively new delivery model. Architects and CMs may have a tendency to revert back to traditional roles.

PLAN OF ACTION: Although the DA process produces a more efficient, collaborative design process, care must be taken to ensure that the collaborative process continues throughout construction. During construction, there are inevitable owner concerns. That’s why it’s important to have established a process to address these changes. The collaborative process can be used to resolve challenges in a quick, cost-effective manner.

OWNER CONCERN: Subcontract administration. The subcontractor might not perform as expected or fall out of line with the budget.

PLAN OF ACTION: It is important to administer a preconstruction contract with the DA subcontractor, which allows the owner to terminate the agreement at any time prior to construction. This acts as a safeguard when a subcontractor’s pricing is not in line with the budget, and there is no reasonable way to get to the budget; in such a case, the owner would have reasonable cause to terminate the subcontractor’s contract. In this situation the trade package would need to be bid, which could push back the schedule depending on the selection process.

OWNER CONCERN: Obtaining competitive pricing. Some owners believe early involvement with subcontractors and the construction manager in the project precludes them from receiving competitive bids.

PLAN OF ACTION: Because the construction team is hired early in the design phase, the Building Team can obtain benchmark prices during the programming phase, making competitive pricing feasible. The Building Team can also obtain nonbinding preliminary price proposals during the DA selection process based on initial plans, such as schematic drawings; binding final prices can be submitted upon completion of the plans.

OWNER CONCERN: Added costs of the DA process. Design-assist may add time and cost to the design phase of the project due to additional collaboration with subcontractors and added time to procure services.

PLAN OF ACTION: The reductions achieved in construction cost and schedule should offset additional costs during the design phases, making design-assist advantageous overall.

OWNER CONCERN: Design liability. Greater collaboration among the architect, engineer, subcontractors, and construction manager might raise questions about who has responsibilities and design liability throughout the process.

PLAN OF ACTION: The project team should clearly set obligations and liabilities of the team members with respect to plans, specifications, and the building information model (if applicable) to overcome this concern. You should also develop a design-assist execution plan to identify roles, responsibilities, and deliverables for all team members.

Related Stories

| Oct 7, 2011

GREENBUILD 2011: Schools program receives grant to track student conservation results

To track results, schools will use the newly developed Sustainability Dashboard, a unique web-based service that makes tracking sustainability initiatives affordable and easy.

| Oct 6, 2011

GREENBUILD 2011: NEXT Living EcoSuite showcased

  Tridel teams up with Cisco and Control4 to unveil the future of green condo living in Canada.

| Oct 4, 2011

GREENBUILD 2011

Click here for the latest news and products from Greenbuild 2011, Oct. 4-7, in Toronto.

| Oct 4, 2011

GREENBUILD 2011: Methods, impacts, and opportunities in the concrete building life cycle

Researchers at the Massachusetts Institute of Technology’s (MIT) Concrete Sustainability Hub conducted a life-cycle assessment (LCA) study to evaluate and improve the environmental impact and study how the “dual use” aspect of concrete.

| Sep 28, 2011

Look who's coming to BD+C's Under-40 Leadership Summit

AEC industry "under-40 superstars" from top design and construction firms have signed up for BD+C's "Under-40 Leadership Summit."

| Sep 28, 2011

Bradley sponsors design studio on intelligent buildings for UWM SARUP

 The studio is taught by Gregory D. Thomson, assistant professor and co-director of the Institute for Ecological Design at UWM.

| Sep 23, 2011

ABI turns positive after four monthly declines

On the heels of a period of weakness in design activity, the Architecture Billings Index (ABI) took a sudden upturn in August.

| Sep 19, 2011

Portland team hired as LEED and commissioning consultants for $5.5B downtown sustainable project in Qatar

The $5.5 billion sustainable downtown regeneration project underway by Msheireb Properties will transform a 76 acres site at the centre of Doha, Qatar’s capital city, recreating a way of living that is rooted in Qatari culture, attracting residents back to the city center and reversing the trend for decentralization.

| Sep 14, 2011

USGBC L.A. Chapter's Green Gala features Jason McLennan as keynote speaker

The Los Angeles Chapter of the nonprofit USGBC will launch its Sustainable Innovation Awards this year during the chapter's 7th Annual Green Gala on Thursday, November 3.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021