flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold

WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold

Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby.


By By BD+C Staff | February 13, 2012
The project is designed to 25% water use reduction and 21.28% lighting power density reduction.

At Morristown Memorial Hospital in Morristown, N.J., the renovation of a single floor, Simon Level 5, has received a Gold LEED Commercial Interiors certification from the USGBC. The 14,070 square foot project, the renovation of a 1948 semi private room bed floor into an in-patient unit focused on oncology patients, encompasses 30 patient rooms and supportareas including a nurses station, pharmacy, a staff lounge, two waiting rooms and administrative offices. Although small in scope the project has had high impact at the hospital, demonstrating that sustainability can be achieved despite the challenges of being located in an existing building.

Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby. Patient rooms are located along the perimeter of the building, making them easily accessible to nursing staff. Newly installed air-handling units on the building’s rooftop and deck-to-deck wall partition provide patient room ventilation and air conditioning.

The project is designed to 25% water use reduction and 21.28% lighting power density reduction. In addition, 77% of construction waste was recycled and diverted away from the landfill.  Sustainable project materials and high indoor environmental quality (IEQ) were a focus of the design and construction, resulting in a12.6% materials with recycled content, 61% manufactured regionally, and 13 of 35 LEED points achieved by the project coming from the IEQ category. The hospital’s decision to reuse all of the patient beds resulted in 68% furniture reuse for the project, thus capitalizing on existing resources to conserve the new. The project’s urban location with a transportation network and community connectivity also contributed towards the LEED certification.

In an effort to make the entire Simon building more energy efficient, improvements were made to other portions of the building outside the immediate project scope. The two new air-handling units were sized not only serve the 5th floor, but to improve the indoor air quality of floors 2-4 as well. Improvements were also made on the Simon building rooftop where fifty-three percent of the building’s rooftop was replaced with a new, high-reflective, roofing material. BD+C

Related Stories

High-rise Construction | Apr 17, 2015

Construction begins on Goettsch Partners-designed Nanning China Resources Center Tower

The tower's design is derived from its multiple uses, which include 170,000 sm of Class A office space, 5,000 sm of boutique retail, and a 45,000-sm luxury Shangri-La hotel.

Museums | Apr 16, 2015

SANAA and Snøhetta tie at first place for Budapest museum bid

The two firms submitted designs for the New National Gallery and Ludwig Museum, one of five planned museums to be constructed in a park just outside the urban center of Hungary’s capital. 

High-rise Construction | Apr 16, 2015

Construction begins on Seattle's Tibet-inspired Potala Tower

Construction on the 41-story Potala Tower in Seattle finally kicked off following a ground-breaking ceremony seven months ago.

Architects | Apr 14, 2015

Jeanne Gang, Bjarke Ingels among participants for inaugural Chicago Architecture Biennial

Some big names include Bjarke Ingels Group and Studio Gang Architects

Sports and Recreational Facilities | Apr 13, 2015

USTA breaks ground on what will be the country’s largest tennis complex

The 63-acre facility is being positioned as a cornerstone for a sports innovation and performance district in Lake Nona, Fla., a 7,000-acre master planned community that continues to expand.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 10, 2015

Prefab saves the day for Denver hospital

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 10, 2015

Virtual collaboration helps complete a hospital in 24 months

PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.

Building Team Awards | Apr 10, 2015

New arts venue reinvigorates Virginia Tech's campus

The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021